Questions # 81:

A project team has been assigned to improve the customer service of a retail company. The team has conducted a thorough analysis of the existing process, determined areas of improvement, and identified the desired outcomes of the project. Which of the following best describes this analysis?

Options:

A.

Process improvement

B.

Business objectives

C.

Current state vs. future state

D.

Project success criteria

Questions # 82:

Which of the following would be the most helpful in providing customers with an application accessible via a web browser?

Options:

A.

IaaS

B.

SaaS

C.

PaaS

D.

XaaS

Questions # 83:

Which of the following best describes the role of a PM for a CRM system?

Options:

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Questions # 84:

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

Options:

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Questions # 85:

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

Options:

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Questions # 86:

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Options:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Questions # 87:

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

Options:

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Questions # 88:

A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?

Options:

A.

Infrastructure end of life

B.

Company reorganization

C.

Digital transformation

D.

Major cybersecurity event

Questions # 89:

Which of the following should occur first when planning maintenance windows?

Options:

A.

Diagnose potential areas for concern.

B.

Notify the customer base.

C.

Determine a rollback plan.

D.

Understand the organization's production cycle.

Questions # 90:

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

Options:

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.