Waratah Hospital, located in Australia, plans to relocate many data-center services to a new facility. (The remaining legacy data center is not included in this project.) Waratah Hospital has engaged an external consultant to help design the new data-center network.
Based on the data-center network-infrastructure requirements, the external consultant has produced a high-level design. The design document is summarized below.
Requirements and information:
Six racks in the data-center room (a single row).
Redundant top-of-rack leaf switches with back-to-front cooling in every rack, providing 10/25 Gbps connectivity to servers, storage, and other devices.
Four 100 GbE uplinks per leaf switch.
The customer requested that all switch ports face the rear of the rack racks (hot aisle).
OOB management for servers, storage, and network devices must be provided through an external switch with back-to-front cooling. This switch must be included in the solution. One OOB switch provides connectivity for two racks.
Core equipment for the OOBM network is being reused.
Middle-of-row spine switches.
The data center must connect to the hospital building through links providing 400 Gbps.
Internet access is provided through an existing firewall cluster containing two firewalls, with one firewall in each data room. The second firewall operates in standby mode, and VRRP is used on the firewalls for failover. The data-center network must connect to these firewalls through links totaling 100 Gbps.
The external link is a direct dark-fiber link based on single-mode fiber (OS2). The distance to the main hospital is 1.5 KM. The links will terminate on two core switches in the hospital.
The customer also requires:
99.999% uptime for this life-critical environment.
Planned and unplanned downtime must be minimized.
Software upgrades are allowed only once per year, with close to zero downtime.
All life-critical resources are accessed locally, and all resources reside within the hospital campus.
Waratah Hospital requires a highly secure data-center environment. Encrypted wire-speed connectivity between the data room and the hospital is mandatory because the link between the buildings crosses a public road.
Waratah Hospital has a mix of virtualized (vSphere) servers, Nutanix storage, bare-metal servers, backup servers, and other devices.
In the past, the hospital experienced a security breach that resulted in data loss, network downtime, and identity theft.
Refer to the scenario. A junior colleague recommends deploying CX 8325-32C BF 6F 2AC Bundle switches as border leaf switches. What concern should you raise about this plan?
You are replacing the access layer in a customer data center network that uses VMware NSX. The customer has identified several subnets outside the VMware platform for which the customer wants to add overlay routing.
What high-level plan will work for this customer?
A customer’s data center uses structured cabling based on MMF OM5. The customer plans to upgrade the spine switches in their spine-and-leaf topology. A primary objective of this upgrade is eventually to support 400GbE leaf-to-spine links. However, many leaf switches will continue to support 100GbE uplinks for some time.
What is a valid recommendation for the spine switches?
When you create an endpoint group in Aruba Fabric Composer, which option should you choose in the Endpoints section to protect the hypervisor?
You are proposing an L3 spine-and-leaf topology to a customer. The solution includes four CX 8325-32C switches at the spine and two CX 8325-48Y8C switches in every server rack. For this customer, the leaf switches in one rack will provide the border-leaf functionality. The customer’s data center is expanding, and the customer asks how many total server racks this solution can scale to support.
What should you say?
A customer has deployed CX 10000 switches, Fabric Composer, and Pensando Policy and Services Manager (PSM). The switches are discovered in PSM, but no VRFs or networks have been added. The customer now wants to begin by applying micro-segmentation to one network. They state that they plan to add a policy containing rules that permit desired traffic from endpoints in this network. They will apply it to the network as an egress policy. At this time, they will not add any other networks to PSM or apply policies to them.
What warning should you raise to the customer about this plan?
Waratah Hospital, located in Australia, plans to relocate many data-center services to a new facility. (The remaining legacy data center is outside this project’s scope.) Waratah Hospital has engaged an external consultant to help design the new data-center network.
Based on the data-center network-infrastructure requirements, the external consultant has produced a high-level design. The design document is summarized below.
Requirements and information:
Six racks in the data-center room (a single row).
Redundant top-of-rack leaf switches with back-to-front cooling in every rack, delivering 10/25 Gbps connectivity to servers, storage, and other devices.
Four 100 GbE uplinks per leaf switch.
The customer requested that all switch ports face the rear of the racks (the hot aisle).
OOB management for servers, storage, and network devices must be delivered through an external switch with back-to-front cooling. This switch must be included in the solution. One OOB switch provides connectivity for two racks.
Core equipment for the OOBM network is being reused.
Middle-of-row spine switches.
The data center must connect to the hospital building through links providing 400 Gbps.
Internet access is supplied through an existing firewall cluster with two firewalls, one in each data room. The second firewall operates in standby mode, and VRRP is used for firewall failover. The data-center network must connect to these firewalls with links totaling 100 Gbps.
The external link is a single-mode-fiber (OS2) dark-fiber direct link. The distance to the main hospital is 1.5 KM. The links will terminate on two core switches in the hospital.
The customer also requires:
99.999% uptime for this life-critical environment.
Planned and unplanned downtime must be minimized.
Software upgrades are permitted only once per year, with close to zero downtime.
All life-critical resources are accessed locally, and all resources are within the hospital campus.
Waratah Hospital requires a highly secure data-center environment. Encrypted wire-speed connectivity between the data room and the hospital is mandatory because the link between the buildings crosses a public road.
Waratah Hospital has a mix of virtualized (vSphere) servers, Nutanix storage, bare-metal servers, backup servers, and other devices.
Previously, the hospital experienced a security breach that caused data loss, network downtime, and identity theft.
Refer to the scenario. You are deciding between the CX 9300 and CX 8325 switches for the border leaf switches. Which hard customer requirement affects this decision?
A customer is deploying a cluster of twelve servers for AI workloads. Each server has four NVIDIA GPUs connected through NVLink. Each server supports 400 GbE connectivity on as many as six ports; however, you may recommend fewer ports. You have been asked to design a network for the servers’ backend AI interconnect.
Based on HPE Networking recommendations for this workload, how many CX 9300-32D switches should you propose?
Waratah Hospital, located in Australia, plans to relocate many data-center services to a new facility. (The remaining legacy data center is outside the scope of this project.) Waratah Hospital has engaged an external consultant to help design the new data-center network.
Based on the data-center network-infrastructure requirements, the external consultant has produced a high-level design. The following summarizes the design document.
Requirements and information:
Six racks in the data-center room (a single row).
Redundant Top-of-Rack leaf switches with back-to-front cooling in every rack, delivering 10/25 Gbps connectivity for servers, storage, and other devices.
Four 100 GbE uplinks per leaf switch.
The customer requested that all switch ports face the back of the racks (hot aisle).
OOB management for servers, storage, and networking must be delivered through an external switch with back-to-front cooling. This switch must be included in the solution. One OOB switch provides connectivity for two racks.
Core equipment for the OOBM network is being reused.
Middle-of-row spine switches.
The data center must connect to the hospital building through links providing 400 Gbps.
Internet access is supplied through an existing firewall cluster with two firewalls, with one firewall in each data room. The second firewall runs in standby mode, and VRRP is used on the firewalls for failover. The data-center network must connect to these firewalls using links totaling 100 Gbps.
The external link is a dark-fiber direct link using single-mode fiber (OS2). The distance to the main hospital is 1.5 KM. The links will terminate on two core switches in the hospital.
The customer also requires:
99.999% uptime for this life-critical environment.
Planned and unplanned downtime must be minimized.
Software upgrades are permitted only once per year with close to zero downtime.
All life-critical resources are accessed locally, and all resources reside within the hospital campus.
Waratah Hospital requires a highly secure data-center environment. Encrypted wire-speed connectivity between the data room and the hospital is mandatory because the link between the buildings crosses a public road.
Waratah Hospital has a mix of virtualized (vSphere) servers, Nutanix storage, bare-metal servers, backup servers, and other devices.
Previously, the hospital experienced a security breach that caused data loss, network downtime, and identity theft.
In this scenario, the customer servers are HPE Servers. For the iLO ports, you propose one 6300M switch per rack. What is the best practice for connecting these switches to the data-center data plane?
You have been asked to help design an HPE Aruba Networking CX network solution that connects AI servers to file storage. The solution must support NFS over RDMA and deliver 400 GbE links to the edge. The current design uses leaf and spine switches that carry all traffic in VXLAN tunnels. Every switch is a CX 9300-32D switch.
What is one correction you should make to the design?