Questions # 1:

A PMO professional is responsible for supporting programs and projects at a government organization. The PMO professional has been tasked with providing project management tools and information systems that will enable the organization's project managers to achieve their goals effectively.

Which two actions should the PMO professional take? (Choose 2)

Options:

A.

Adapt the project management tools and information systems to be compliant with government regulations.

B.

Meet with the project managers to understand their needs and any gaps in using project management tools and information systems.

C.

Provide the project managers with a list of project management tools and information systems in the market and have them pick.

D.

Enhance the organization's project management tools and information systems to meet the specific needs of the project managers.

Questions # 2:

A PMO professional is supporting project managers who are engaged in launching a new advertising campaign for a marketing agency. One of the project managers seeks guidance on effectively managing the stakeholders to ensure project success and client satisfaction.

What should the PMO professional do?

Options:

A.

Tailor communications to the stakeholders who are directly impacted by the project outcomes.

B.

Keep communication with stakeholders at a high level to avoid overwhelming them with too many project details.

C.

Prioritize communication efficiency by limiting communication to weekly stakeholder surveys focused on stakeholders' concerns.

D.

Maintain multiple lines of communication with all stakeholders to gather feedback, address concerns, and develop solutions.

Questions # 3:

A PMO professional leading a global PMO wants to ensure that the PMO's services continue to evolve and deliver value to customers.

Which approach best supports the PMO professional in achieving this goal?

Options:

A.

Implement a continuous improvement process to regularly update the PMO methodologies.

B.

Establish regular communication channels with PMO customers to understand their evolving needs.

C.

Adopt the latest project management methodologies, including training for project managers.

D.

Benchmark the PMO's performance against other PMOs in the industry to ensure continuous improvement.

Questions # 4:

Two years ago, a software company implemented an agile culture and adopted Scrum as a framework for product development. During those 2 years, the company's senior management struggled with the link between the product value generated and the business objectives.

What should the PMO professional do to bridge this gap?

Options:

A.

Develop a dashboard to show the product portfolio's progress.

B.

Advise the board to move to a hybrid approach for its product development.

C.

Create a benefits map for the company's initiatives and products.

D.

Provide a report with agile team metrics, including velocity and burn charts.

Questions # 5:

A food industry company recently acquired a new company. To ensure a quick integration, several project managers are assigned to combine the product portfolios. The PMO for the integration program was informed by the project managers that they encountered a regulatory compliance change regarding several products manufactured by the acquired company. This is having a significant impact on the ongoing product portfolio integration.

Which actions should the PMO professional take to support the quick adaptation to these changes in the future?

Options:

A.

Review the issue with the project managers and make sure they are capturing problems in the lessons learned register so that information can be leveraged for similar future projects.

B.

Schedule a regular touchpoint between the project managers and the regulatory experts for the adjustment of project plans to incorporate changes in regulatory requirements or market conditions.

C.

Standardize all project management processes to ensure uniformity across all product portfolio integration projects.

D.

Develop a training for the project managers with the regulatory department that emphasizes the importance of complying with regulatory requirements.

Questions # 6:

A PMO currently serves all investment initiatives within a company and has reached a high level of maturity. The executive leadership team is enthusiastic about PMO value, and all PMO customers promote its services. The PMO professional who leads the PMO has received information that the innovation portfolio struggles with its initiatives.

What should the PMO professional do first to support the innovation portfolio?

Options:

A.

Demonstrate to the innovation team how the PMO supports effective delivery of investment projects within the organization.

B.

Engage with the executive team to assess current strategic initiatives and align services to drive additional value.

C.

Ask for a mandate from the executive team to support the innovation initiatives.

D.

Meet with the innovation manager and understand their situation to see how the PMO can support them.

Questions # 7:

A PMO was just established in a large organization. The PMO team identified all potential PMO customers and analyzed them based on their power and interest. The list of customers was much too long and the PMO's capacity to nurture them all is not sufficient.

What should the PMO professional do to move toward developing the service catalog?

Options:

A.

Interview executive leadership, understand their expectations, and generalize the findings as they are the main decision makers.

B.

Consider all customers, categorize them, and decide on how to retrieve information from the different groups of customers.

C.

Focus on the middle and top levels of management and incorporate resource expectations for when the PMO will have sufficient resources to serve all of the customers.

D.

Interview the portfolio, program and project managers; understand their needs; and develop a service catalog based on their interests as they are the experts.

Questions # 8:

A PMO is ready to deploy new services that address the current, confirmed needs of the organization.

What is the first thing the PMO professional should do to ensure optimal implementation of the PMO services to meet customer expectations?

Options:

A.

Tailor educational activities with key customers based on their requests.

B.

Define a step-by-step approach to deploy the new PMO services.

C.

Create and distribute detailed user guides and other educational information.

D.

Educate all customers on the PMO services available.

Questions # 9:

The executive management team for a healthcare company is discussing the second quarter's low result in the customer satisfaction score, which is a key performance indicator (KPI). One of the executives shares concerns about wasting efforts on projects and initiatives without being able to keep up with competitors and increase the customer satisfaction score.

Which action should the PMO professional take to avoid such a situation?

Options:

A.

Avoid the customer satisfaction metric analysis when assessing projects.

B.

Support the reevaluation of the strategic plan by the executives.

C.

Ask to review the customer satisfaction metrics.

D.

Establish a customer experience department.

Questions # 10:

During the execution phase of the project, the PMO professional notices that a project team is consistently falling behind schedule. Despite the best efforts of the PMO to provide additional resources and support, the team continues to struggle with meeting the deliverables. The PMO professional determines that the root cause of the delays is poor communication among team members.

Which two tasks should the PMO professional take? (Choose 2)

Options:

A.

Replace some resources from the project team to make collaboration among the team more efficient.

B.

Implement project management software to facilitate real-time collaboration and communication among team members.

C.

Reallocate additional resources from other project teams to compensate for the delays and ensure timely completion.

D.

Escalate the issue to senior management and request additional budget for outsourcing certain project tasks to external vendors.

E.

Provide a series of project management training sessions to improve communication skills and foster better teamwork.