Questions # 21:

Technicians are tasked with performing product upgrades at customer sites. During the upgrade process, a new product is installed to replace the obsolete product. For reporting purposes, the information about the obsolete and upgraded products, as well as the customer for which the upgrade is done should be tracked in Salesforce.

Which object should an admin configure to support this process?

Options:

A.

Child Asset

B.

Asset Warranty

C.

Asset Relationship

D.

Maintenance Asset

Questions # 22:

Universal Containers is starting to test Global Optimization. They see that not all Service Appointments sent into Optimization are being scheduled, which causes large amounts of white spaces for Service Resources who meet all the criteria to be scheduled for the appointments.

Which three actions can an architect take to investigate UC's issues? (Choose 3 options)

Options:

A.

Review the 'Pinned Statuses' for Global Optimization under 'Field Service Settings'

B.

Ensure the appointments to be optimized are visible within the appointment list View

C.

Review the settings within the lightbox when initiating optimization from the Gantt

D.

Enable, configure, and review 'Optimization Insights' on the 'Optimization Request' Object

E.

Ensure the default Scheduling Policy is in focus on the Gantt Chart before optimizing

Questions # 23:

Which three topics should a consultant raise during the project scoping discussion of a field service implementation?

Options:

A.

Work Parameters: how work is being defined

B.

Sprint Review: to review what will be done during the sprint cycle

C.

Terminology: translate objectives and priorities into Field Service

D.

Project Objectives: what is essential

E.

Solution Design: request for acceptance

Questions # 24:

Green Energy Solutions would like to become more competitive by providing a better service experience to prospects calling in to request an initial assessment visit.

What should a consultant recommend to the business in order to achieve such a goal?

Options:

A.

Increase the length of the arrival window offered to the customer from 4 hours to 8 hours, which gives the customer more flexibility in preparing for the visit

B.

Reduce the length of the arrival window offered to the customers from 4 hours to 2 hours, taking into consideration that this change might impact the quality of optimization

C.

Reduce the length of the arrival window offered to the customers from 4 hours to 2 hours, which will also allow further flexibility when running optimization

D.

Increase the length of the arrival window offered to the customer from 4 hours to 8 hours, as it will ensure that the assessment visit will be completed before the arrival window ends

Questions # 25:

Universal Containers (UC) outsources all maintenance work to contractors, based on a contract that is renewed on a yearly basis. When a contract is terminated, UC would like to ensure that new maintenance Work Orders will not be scheduled for the terminated contractor.

Which two steps should an admin take to ensure their requirements are met?

Options:

A.

Add the 'Active Resources' Work Rule to the Scheduling Policies

B.

Delete the Service Resource

C.

Deactivate the Service Resource

D.

Add the 'Excluded Resources' Work Rule to the Scheduling Policies

Questions # 26:

ACME Utilities would like to include their Assets (such as 'Cranes' and 'Excavators') in scheduling along with the Service Resources. As there might be a limited number of Assets for a particular job, they want those to be included in the scheduling process so that asset usage can be optimized.

How can this be achieved?

Options:

A.

On the Asset record, set the Boolean field 'Use for Scheduling' to 'True'

B.

Add the Asset as a lookup on the Service Appointment being scheduled

C.

From the 'Dispatcher Console', after pressing 'Schedule' action, select 'Include Assets'

D.

The customer will need to purchase licenses for the Assets and then set them up as Service Resources

Questions # 27:

Universal Containers has many service centers across the country in which spare parts and other inventory items are stored. Every morning, technicians are required to arrive at the service center closest to their home and pick up inventory items based on their work assignments. At the end of the day, technicians travel back to the service center to return any unused or damaged parts (travel from home to the service center and from the service center back home is at the technicians' expense).

How should the admin configure the Service Territory Member address?

Options:

A.

Use the technician's home address

B.

Use the customer's address

C.

Use the address of the service center that the technician is assigned to

D.

Use the address of the first appointment of the day

Questions # 28:

Universal Containers' dispatchers would like to alert technicians when emergency appointments are scheduled and dispatched to them.

Which two configurations should be recommended by the consultant to achieve this?

Options:

A.

Create a Process Builder that checks the 'In Jeopardy' field when a Service Appointment is dispatched and flagged as 'Emergency'

B.

Configure Custom Notifications for Field Service Mobile

C.

Configure 'In Jeopardy' alerts for Field Service

D.

Create a flow that triggers a Custom Notification to the Assigned Resource when a Service Appointment is dispatched and flagged as an 'Emergency'

Questions # 29:

Universal Containers outsources maintenance work to a third-party contractor who has agreed to provide a total of 20 hours of availability per day between 9:00 AM and 5:00 PM. Universal Containers' internal resources work 8:00 AM to 8:00 PM including overtime.

How should a consultant configure the contractor resources to meet this requirement?

Options:

A.

The contractor will be 'Capacity Based Resource' with different Operating Hours than the internal resources, and the maintenance skill

B.

Modify the Scheduling Policy to prefer contractors

C.

Create a Service Territory for contractors to ensure that maintenance work is assigned only to them

D.

The contractor will be a 'Named Resource' with Operating Hours of 8:00 AM till 11:00 PM, and 'Designated Work' for maintenance work between 9:00 AM and 5:00 PM

Questions # 30:

Universal Containers installers are required to complete a standardized quality checklist that includes data inputs as well as capturing some pictures of the completed installation.

How should a Field Service consultant set up the mobile experience for those installers?

Options:

A.

Leverage 'Work Plans' and a flow to launch from a 'Work Step'

B.

Create fields on the Service Appointment and create a Service Appointment 'Record Update' action for the quality check items and leverage 'Chatter' to post images

C.

Give complete edit access to the mobile app so the installers have the flexibility to update what they need

D.

Use 'Deep Linking' in order to achieve this requirement