Questions # 31:

What is included in the Inspect and Adapt agenda?

Options:

A.

Program backlog refinement

B.

System Demo

C.

Quantitative and qualitative measurement

Questions # 32:

At which Tuckman stage would an ART be if it is improving engineering practices and fostering more effective communication?

Options:

A.

Storming

B.

Performing

C.

Forming

D.

Norming

Questions # 33:

What is one way to develop sufficient Architectural Runway for the Agile Release Train?

Options:

A.

Ask the teams to commit only to Enablers as their Program Increment (PI) Objec-tives during the PI Planning event and address Features as uncommitted objec-tives for the first PI

B.

Create alignment with the System Architect and Product Management that the first Program Increment (PI) is all about Enablers in order to plan for creating business value in the second PI

C.

Ask the Business Owner which Enablers have high business value

D.

Work with Product Management and System Architects to identify future Features and determine the Enablers to achieve them

Questions # 34:

What is one example of a servant leader behavior pattern?

Options:

A.

Thinks about the day-to-day activities

B.

Uses authority rather than persuasion when necessary

C.

Understands and empathizes with others

D.

Focuses on individual task Metrics

Questions # 35:

What is one reason why the ART predictability measure is important?

Options:

A.

It identifies under-performing teams

B.

It demonstrates the need to fix the scope at the beginning of the PI

C.

It indicates where the Solution is ready to be released

D.

It allows the business and other stakeholders to plan effectively

Questions # 36:

When planning for a distributed Program Increment (PI) Planning event with a large dif-ference in time zones, what are two key preparation and facilitation focus areas for a Re-lease Train Engineer (RTE)? (Choose two.)

Options:

A.

Share the outcomes of preparation meetings with local Scrum Masters so they can arrange local rooms

B.

Have a single RTE and technical support person that acts as a central point of communication for all locations

C.

Adjust the PI agenda to 2.5 – 3 days, allowing for overlapping hours

D.

Split up the PI Planning event per time zone and then have the final plan review, confidence vote, and planning retrospective as one centralized meeting

E.

Arrange and test presentation audio and video connectivity in all locations

Questions # 37:

Some teams are having difficulty identifying where they might make process improve-ments. How might the RTE support them?

Options:

A.

Encourage the team to perform regular self-assessments and discuss findings

B.

Conduct a survey to identify the worst problems the team is having

C.

Observe the team's ceremonies and share observations

D.

Run longer I&A meetings to brainstorm improvement items

Questions # 38:

What action can result in reduced collaboration between teams during the Program Increment (PI) Planning event?

Options:

A.

Skip the Inspect and Adapt event

B.

Include inexperienced team members

C.

Start the Agile Release Train without a System Team in place

D.

Overprepare for PI Planning

Questions # 39:

Which two key skills does a Release Train Engineer bring to economic prioritization? (Choose two.)

Options:

A.

Do research and data collection for cost of delay factors

B.

Determine job size by surveying Scrum Masters of impacted teams

C.

Facilitate stakeholder collaboration

D.

Coordinate Lean Portfolio Management by providing feedback for cost of delay factors

E.

Understand and facilitate weighted shortest job first

Questions # 40:

What practice can help to identify bottlenecks in the flow of work?

Options:

A.

Visualizing the flow of all work and track progress of individual items

B.

Comparing transaction costs, holding costs and business value realization

C.

Measuring lead time for all work in progress

D.

Modeling overall process flow during value stream identification