Questions # 1:

A Product Owner is needed for every:

(choose the best answer)

Options:

A.

Product.

B.

Portfolio.

C.

Program.

D.

All of the above.

Questions # 2:

Product A is a big revenue producer; it has:

. High Current Value and Low Unrealized Value.

Product B is a new product with a lot of potential; it has:

. Low Current Value and High Unrealized Value.

Using those two data points and taking a long-term view, which of the options below should you

pursue?

(choose the best answer)

Options:

A.

Weight your investment toward Product B; since it has more potential.

B.

Weight your investment toward Product A; you do not want to risk losing customers.

C.

Invest equally in both products.

Questions # 3:

Every Scrum Team must have a Product Owner and Scrum Master.

(Choose the best answer)

Options:

A.

Yes, and each Scrum Team ' s performance may be affected by how much they participate during the Sprint as a Scrum Master or Product Owner.

B.

No.

C.

Yes, and they must be 100% dedicated to each team.

Questions # 4:

Your product ' s nearest competitor has lower market share, but has higher customer

satisfaction, though they lack some key features of your product. You are losing market share

to them as customers discover them. They release 3 times faster than you, which is helping

them to win customers. What should you do first in response?

(choose the best answer)

Options:

A.

Add features to your next release that you think will retain and win customers.

B.

Lower your product ' s price to make it more attractive to new and existing customers.

C.

Improve your time-to-market and rate of innovation to improve your responsiveness.

D.

Find new markets for your product that your competitor is not yet in.

Questions # 5:

You are a Product Owner for a product that publishes customer usage rates by feature.

An influential stakeholder does not believe the data showing the usage rates, and insists that a

particular feature is essential, despite data showing low usage rates. The stakeholder believes

that measuring feature usage is a waste of time.

As Product Owner you have confirmed that the data is accurate and believe that the data is

valuable to help you and your team. What should you do?

(choose the best answer)

Options:

A.

Continue measuring feature usage and use it to inform your decisions, but do notpublish it.

B.

Continue to measure and publish the data, to provide openness and transparency,and use it to inform your decisions.

C.

Stop measuring feature usage to appease the stakeholder.

Questions # 6:

Who is accountable for clearly expressing Product Backlog items?

(choose the best answer)

Options:

A.

The Developers.

B.

The Scrum Master.

C.

The Scrum Master, or the Scrum Master may have the Developers help.

D.

The Product Owner, but the Product Owner may appoint a proxy on the Scrum Team to do the work.

E.

The Scrum Master, or the Scrum Master may have the Product Owner do it.

Questions # 7:

What percent of the time should a Product Owner dedicate to the Scrum Team?

(choose the best two answers)

Options:

A.

100%.

B.

Enough time to avoid the waste that is created by delaying answers to theDevelopers.

C.

As much as the stakeholders want to budget. Business analysts take over therole the rest of the time.

D.

40%, or more if the stakeholders agree.

E.

Enough time to ensure that the product Increment is valuable and useful.

F.

Just enough time to keep the Developers from complaining.

Questions # 8:

The Developers inform the Product Owner during the Sprint that they are not likely to complete

everything they forecasted. What would you expect a Product Owner to do?

(choose the best answer)

Options:

A.

Reduce the scope of the Sprint, if possible, to still meet the Sprint Goal.

B.

Skip Product Backlog refinement activities.

C.

End the Sprint, since the goal cannot be achieved.

D.

Change the Sprint Goal to match what the Developers can deliver.

E.

Inform management that more resources are needed.

Questions # 9:

A " cone of uncertainty " can be used to do what?

(choose the best answer)

Options:

A.

Represent the relative level of difficulty for predicting the velocity of individual teammembers.

B.

Rapidly identify and prioritize all uncertainties.

C.

Determine whether to cut quality, similar to the " Iron Triangle " of projectmanagement.

D.

Visualize the uncertainty of the potential value that a Scrum Team delivers over time.

Questions # 10:

You are a Product Owner for a product with a rapidly declining customer base.

Despite data that indicates the decline is due to a shrinking market, rather than a lack of new

features, an influential stakeholder insists on adding more features to attract new customers.

The influential stakeholder also says that if you do not add new features you risk losing your

most profitable customer.

Which two of the following actions might you take?

(choose the best two answers)

Options:

A.

Collaborate with the stakeholder to run a small experiment to validate theiropinion.

B.

Collaborate with other stakeholders and use a voting system to decide whichoptions should be considered.

C.

Acknowledge the views of the influential stakeholder but decline to add morefeatures to the product.

D.

Agree with the stakeholder and add features to the Product Backlog as it mightincrease your customer base.