Questions # 81:

Please read this scenario prior to answering the question

Your role is that of an Enterprise Architect In a company that develops wind turbines for use in wind farms. The company has multiple manufactunng facilities, in North America, Asia, and Europe. Each of these facilities supplies the power industry In Its region. Most of the facilities are wholly owned by the company, but those In Asia are jointly owned with local partners.

The company has a mature Enterprise Architecture practice supported by a cross-functional Architecture Board and uses the TOGAF standard.

The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels. In order to do so this will require wind turbines to be installed over large areas and in areas of higher wind resources. In particular offshore wind farms can contribute substantially more energy than land stationed turbines.

The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system, that will produce up to 20% more energy. This new design is ready to go Into production.

As part of putting the new design into production, adjustments to the automated assembly processes need to be made. A pilot architecture project at a single location has defined an updated approach for controlling the automated systems used to perform final assembly and quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the wortc needed to implement and deploy the new automated system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and a low blade failure rate.

Refer to the Scenario

You have been asked to recommend the best approach to address the Chief Engineer ' s concern.

Based on the TOGAF Standard, Version 9.2. which of the following is the best answer?

Options:

A.

You would review the Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. Where applicable, you ensure that the contract is legally enforceable. You would schedule compliance reviews at key points in the assembly and quality assurance process to ensure that the work is proceeding in accordance with the Architecture Definition. All deviati

B.

You would create an Architecture Contract to manage and govern the implementation and migration process at each location. For wholly owned facilities, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For facilities jointly owned by local partners, you would ensure that the contract is legally enforceable. You would then ensure that the Architecture Board reviews all deviations from

C.

You would create an Architecture Contract to govern the update to the automated system controller at each location. For facilities managed by partners, you ensure that it is a fully enforceable legal contract, and you would schedule additional compliance reviews at key points in the assembly and quality assurance process. These additional reviews would be for an initial period until no deviations from the contract occur. You recommend that

D.

You would use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You would ensure that the quality of each completed turbine blade at each location is assessed, and any local change requirements identified, if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organ

Questions # 82:

Which of the following best describes the purpose of the Architecture Roadmap?

Options:

A.

It lists work packages on a timeline showing progress towards the Target Architecture

B.

It contains an assessment of the current architecture requirements

C.

It provides for effective communication of the end architecture project to the stakeholders

D.

It forms the basis of a contractual agreement between the sponsor and the architecture organization

E.

It is sent from the sponsor and triggers the start of an architecture development cycle

Questions # 83:

Please read this scenario prior to answering the question.

You are employed as an Enterprise Architect at a leading global technology enterprise specializing in digital infrastructure, cloud computing, and data-centric innovation. The company provides a vast ecosystem of platforms that serve billions of users across the globe. These platforms span online marketplaces, advanced advertising networks, AI-driven services, productivity tools, and digital entertainment experiences.

The senior leadership within the company is worried about the company’s ability to address all the opportunities around artificial intelligence. They feel that the business is at risk of falling behind its competitors and that significant changes are necessary for the business to remain competitive. Most senior leaders feel that operations need to be more efficient and that the organization needs to change to achieve its future goals.

The company has an established Enterprise Architecture program based on the TOGAF standard, sponsored jointly by the Chief Information Officer and senior executives. In your role as an Enterprise Architect within the Enterprise Architecture team, you work closely with the business stakeholders in the company as well as the sponsors.

The Chief Executive Officer has decided that reorganizing its subsidiaries around artificial intelligence and machine learning will improve the way the company creates and delivers value. The sponsors have approved a project for the reorganization, which is being led by the Enterprise Architecture team.

The Enterprise Architecture team has developed a strategic architecture that has been approved by the sponsors. It includes an Architecture Vision and high-level definitions of the domain architectures. This sets out a plan over a multi-year period and covers three distinct transformations to implement the reorganization.

The sponsors have read reports that the majority of transformation projects dealing with digital and artificial intelligence are failing. They have made it clear that, prior to approval of the detailed Implementation and Migration Plan, the Enterprise Architecture team needs to address the risks associated with the reorganization. They want assurance that the reorganization will succeed and deliver the promised increases in value for the business.

Refer to the scenario.

The Enterprise Architecture team leader has asked how you would address the request from the sponsors.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

Before preparing the detailed Implementation and Migration Plan, you would review and consolidate the gap analysis results from Phases B to D. This enables you to evaluate the implications related to potential solutions and interdependencies. It is used to identify the transformations required to achieve the proposed Target Architecture. You then assess the readiness of the organization to undergo change and determine an overall direction t

B.

You would apply an analysis and assessment to evaluate the potential risks with the proposed new architecture. This includes the development of a matrix showing the organizational requirements. The degree of change should then be aligned with the corporate operating model to ensure risks are mitigated and minimized. The risk mitigations can then be included within each of the target Transition Architectures. You would then finalize the Arch

C.

You would assess how ready the organization is to change. This includes identification and classification of the risks associated with the transformations, together with an approach to mitigate the risks. This includes identifying dependencies between the set of changes, including gaps and work packages. It also identifies improvement actions to be worked into the Implementation and Migration Plan. The business value, effort, and risk assoc

D.

You would bring together information about potential approaches and produce several alternative target Transition Architectures. You would then investigate the different architecture alternatives and discuss these with stakeholders using the Architecture Alternatives and Trade-offs technique. Once the Target Architecture has been selected, it should be analyzed using a state evolution table to determine the Transition Architectures. A value

Questions # 84:

Please read this scenario prior to answering the question.

You are employed as an Enterprise Architect within an Enterprise Architecture team at a large food services company.

The company has a mature EA practice and uses the TOGAF standard for its architecture work. In addition to using the TOGAF standard, the company uses a number of management frameworks, including project management and operations management. The Chief Information Officer is the sponsor of the EA program within the company.

The company focuses on sales to trade and wholesale customers, for example, restaurants and other food sellers. It sells a variety of products and serves a number of different markets. One of the company’s rivals has launched a competing product range and additional services. They are running a widespread advertising campaign with generous rewards for customers to switch to them. Many of the company’s customers have announced that they are changing to the rival.

The Chief Executive Officer has stated that changes need to be made to address the situation. He wants new markets to be found for the company’s products. The business needs to change direction and address the retail market as well as the existing market.

The company is accustomed to a stable business with a well-established and consistent customer base. It is uncertain whether the company will be able to adapt to changes in its business practices, and whether these changes will be temporary or permanent. The company’s culture presents a potential risk factor.

You have been working with the sales, logistics, production, and marketing teams, enabling the architecture development activity to start. An Architecture Vision, Architecture Principles, and Requirements have all been agreed. As you move forward to develop a possible Target Architecture, you have identified that some of the key stakeholders’ preferences are incompatible. The incompatibilities are focused on time-to-market, cost savings, and the need to bring out a fully featured range of products, but there are additional factors.

Refer to the scenario.

How should you address the incompatibilities between key stakeholder preferences?

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

Make sure that the value preferences and priorities of the stakeholders are understood. Several alternative Target Architectures should be developed, highlighting the gaps between the current state and the alternatives. The features from one or more alternatives should be combined in collaboration with the stakeholders. A formal stakeholder review should then decide which alternative is fit for purpose and should be moved forward with. The

B.

The Architecture Vision, Principles, and Requirements should be used to define a set of criteria for alternatives. A set of architecture views should be created to illustrate the impact of the alternative Target Architectures. The impact on planned projects should be identified, together with the strengths and weaknesses of the alternatives. A formal stakeholder review should be held to decide which alternative to proceed with. The amount o

C.

Review the Stakeholder Map and make sure that the concerns of all department heads have been addressed and represented. The department heads should be involved in resolving the incompatibilities. The Communications Plan should include a report that summarizes the key features of the architecture and how incompatibilities were resolved to satisfy the stakeholders’ requirements. Confirm with each key stakeholder that they are satisfied with h

D.

Given that the Chief Executive Officer has stated that the company must change direction, it is better to compromise on a full product range rather than time-to-market. Just enough of the Target Architecture should be developed to demonstrate fitness of the proposed approach. The description should be limited to where there is a gap from the current baseline. Approval by the stakeholders should be sought to move forward with detailed develo

Questions # 85:

NO: 346

Scenario:

Please read this scenario prior to answering the question

Your role is that of a consultant to the Lead Enterprise Architect in a company that speicializes in luxury electric cars and their powertrain components, and also produces battery-charging equipment. It has its own distribution network, its own showrooms, and sells directly to customers via the internet. The company has four manufacturing facilities, two in the North America, one in Europe, and one in Asia.

A challenge that the company is facing to scale up the number of vehicles coming off the production line to meed customer demand, while maintaining quality. At the moment there are supply chain storages for key electronic components related to the autonomous drive system. In response the this, the research arm of the company has pioneered the development of a new self-driving platform. This new design uses common off-the-shelf components that will allow for a significant increase in overall vehicle production. This new design is ready to go into production.

The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. The TOGAF standard is used for developing the automated manufacturing process and systems used to design, manufacture and test the new design. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

As part of putting the new self-driving platform into production, adjustments to the automated assembly processes need to be made. A pilot architecture project at a single location has defined an updated approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and quality.

Refer to the Scenario

The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer’s concern.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is d

B.

You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed drive assembly at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the a

C.

You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture C

D.

You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architectur

Questions # 86:

Please read this scenario prior to answering the question

You are serving as the Lead Enterprise Architect for a life insurance, annuities, and

pensions company, which has been formed through the merger of three companies.

The company consists of three divisions with the same names and division

headquarters as their predecessors.

The lack of integration between the three divisions has increasingly caused problems

in the handling of customer and financial information. At present, each division

maintains its own applications. Despite an earlier initiative to install a common

application to manage customer, products, and claims information, each division has

different ways of defining its data elements and has customized the common

application to the point where the ability to exchange information is error-prone.

The Chief Information Officer (CIO) has formed an Enterprise Architecture

department, and one of the primary goals in its charter is to coordinate efforts

between the teams in each division. The CIO has also formed a cross-functional

Architecture Board to oversee and perform governance. The TOGAF standard is used

as the basis for the core framework of the Enterprise Architecture program. The

company has an existing team of security architects.

The company has made the decision to introduce a common web portal, contact

center software suite, and document management system. Also the company has

selected a single enterprise-wide customer relationship management (CRM)

application to consolidate information from several applications that exist across the

divisions. The application will be used by each of the divisions and accessed by third

party partners through well-defined interfaces.

The CIO is concerned that the new application must be able to manage and

safeguard customer information in a secure manner that meets or exceeds the legal

requirements of the countries in which the company operates. This will be an

increasingly important capability as the company expands its online services in

cooperation with its external partners.

Refer to the Scenario

As part of the process for initiating the Enterprise Architecture project to rollout the

new application, you are developing a set of architecture principles.

You need to recommend the best approach for this work.

Based on the TOGAF Standard, Version 9.2, which of the following is the best

answer?

Options:

A.

You would define a set of principles that support the preferred best practices

embodied in the Enterprise Architecture department charter. You would publish

the principles on the corporate intranet to ensure widespread acceptance and

compliance within the company. You would then schedule regular periodic

Compliance Assessments with each of the divisions to check that they have

made satisfactory progress toward

B.

You would analyze the mission statements for the company and each of its

divisions, together with the corporate business goals. Based on that analysis,

you would define a set of architecture principles and review them with the CIO.

When developing the principles, you would ensure that they actively promote

the alignment of IT with the business strategies and initiatives of the company.

You would then seek the e

C.

You would review the mission statements for the company and its divisions,

together with the corporate business goals and business drivers. Based on that

review, you would work closely with the key stakeholders and the Architecture

Board to define the architecture principles. You would ensure that they actively

promote the alignment of IT with the corporate business strategies. You would

then hold review meetin

D.

You would gather information from credible industry sources in the insurance

business. Based on that information, you would assess current trends and

apply them to defining a set of principles that embody industry best practices.

You would select architecture principles that do not conflict with each other,

that are consistent, and those that are stable. You would ensure that all the

principles are realistic an

Questions # 87:

Please read this scenario prior to answering the question

Your role is that of an Enterprise Architect in a multinational automotive and clean

energy company. The company designs and manufactures electric vehicles, battery

storage, and solar panels. The company has multiple manufacturing facilities, in North

America, Europe, and in Asia. Most of the facilities are wholly owned by the company,

but two in Asia are jointly owned with local partners.

The company has a mature Enterprise Architecture practice that is supported by a

cross-functional Architecture Board. The TOGAF standard is used for developing the

automated manufacturing process and systems used to design, manufacture and test

the new design. The Chief Information Officer and the Chief Operating Officer co-

sponsor the Enterprise Architecture program.

A challenge that the company is facing is to scale up the number of vehicles coming

off the production lines to meet customer demand. At the moment there are supply

chain shortages for key custom-designed electronic components used in the vehicles.

In response to this, the research arm of the company has pioneered the development

of a revised design using common off-the-shelf components that will allow for a

significant increase in overall vehicle production. This new design is ready to go into

production.

As part of putting the new design into production, adjustments to the automated

assembly processes need to be made. A pilot architecture project at a single location

has defined an updated approach for controlling the automated systems used to

perform final assembly and quality assurance. The Chief Engineer, sponsor of the

activity, and the Architecture Board have approved the plan for immediate

implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement

and deploy the new automated system controller for each location. The Chief

Engineer has expressed concern that a uniform process be employed at each location

to ensure consistency and quality.

Refer to the Scenario

You have been asked to recommend the best approach to address the Chief

Engineer ' s concern.

Based on the TOGAF Standard, Version 9.2, which of the following is the best

answer?

Options:

A.

You would use the Architecture Contracts to manage the architecture

governance processes for the project across the locations. You would ensure

that the quality of each completed vehicle at each location is assessed, and

any local change requirements identified, if necessary. You recommend that if

a deviation from the contract is detected, the Architecture Board should modify

the Architecture Contract to allow

B.

You would review the Architecture Contract for each location, ensuring that it

addresses the project objectives, effectiveness metrics, acceptance criteria,

and risk management. Where applicable, you ensure that the contract is legally

enforceable. You would schedule compliance reviews at key points in the

assembly and quality assurance process to ensure that the work is proceeding

in accordance with the Archit

C.

You would create an Architecture Contract to manage and govern the

implementation and migration process at each location. For wholly owned

facilities, you issue a memorandum of understanding between the Architecture

Board and the implementation organization. For facilities jointly owned by local

partners, you would ensure that the contract is legally enforceable. You would

then ensure that the Architecture Boar

D.

You would create an Architecture Contract to govern the update to the

automated system controller at each location. For facilities managed by

partners, you ensure that it is a fully enforceable legal contract, and you would

schedule additional compliance reviews at key points in the assembly and

quality assurance process. These additional reviews would be for an initial

period until no deviations from the contr

Questions # 88:

Scenario:

Please read this scenario prior to answering the question

Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.

The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels. In order to do so this will require wind turbines to be installed over large areas of higher wild resources. In particular, offshore wind farms can contribute substantially more energy than land stationed trubines.

The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system that will produce up to 20% more energy. This will allow the production of significantly more saleable energy. This new design is ready to go into production.

The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.

Refer to the Scenario

You have been asked to recommend the best approach to address the Chief Engineer ' s concern.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architectur

B.

You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture

C.

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is de

D.

You use the issued Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of the completed blade assembly at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization

Questions # 89:

Please read this scenario prior to answering the question

Your role is consultant to the Lead Architect within a multinational company. The

company is organized into independent operational divisions on a national basis. The

company adapts its marketing messaging to fit each culture group, with the adaptation

of product offerings and manufacturing processes in each market.

The company has a mature Enterprise Architecture (EA) practice and uses the

TOGAF standard as the basis of its architecture framework. In addition to the EA

program, the company has several management frameworks in use, including

business planning, portfolio/project management, and operations management. The

EA program is sponsored by the CIO.

A strategic architecture has been approved that includes consolidation of multiple

applications that have been operating in the production facilities across the divisions.

The goal is to replace the functionality of the existing applications with a new

application running as a single instance in the company ' s primary data center.

Each division has completed the Architecture Definition documentation required to

integrate the new application to meet its own specific manufacturing requirements.

The key corporate change attributes and implementation constraints have been

confirmed. A consolidated gap analysis has been completed which has identified the

gaps across the Business, Data, Application, and Technology domains. Using the gap

analysis results, a review of the consolidated requirements, dependencies, and

interoperability requirements needed to integrate the new application has been

completed. The Business Transformation Readiness Assessment started in Phase A

has been completed. A risk assessment has been completed.

The implementation process is estimated to take four years. Because of the risks

posed by the complexity of the current environment, a phased approach is needed to

implement the target architectures. The Implementation and Migration Plan v0.1, the

draft Architecture Roadmap, and the Capability Assessment deliverables are now

complete.

Refer to the Scenario

You have been asked to recommend the next steps to prepare the final

Implementation and Migration Plan.

Based on the TOGAF Standard, Version 9.2, which of the following is the best

answer?

Options:

A.

You would assess how the plan impacts the other frameworks in use in the

organization. If the plan impacts them, then coordination will be required. You

would then assign a business value to each work package, and identify

projects for the plan, considering available resources and priorities for the

projects. You would then gather the details for the plan, and generate the final

Implementation and Migration Pla

B.

You would review the migration planning outputs, and produce

recommendations for the solution development. You would identify the

priorities, high-level migration strategy, and resources needed for the

development team. You would document the requirements for monitoring

tools, and the performance targets for the implementation. All this information

should be gathered, and the final Implementation and Migration

C.

You would use business value to prioritize the implementation projects and

project increments. This should focus on the return-on-investment criteria set

by the stakeholders, and the performance evaluation criteria used to monitor

the progress of the architecture transformation. You would confirm the

Transition Architecture phases using an Architecture Definition Increments

Table to list the projects. You would

D.

You would place the finalized strategic Architecture Definition Documents and

Transition Architectures under configuration control as part of the ongoing

architecture development cycle. This will ensure that the architecture remains

relevant and responsive to the needs of the enterprise. You would then

produce an Implementation Governance Model to manage the lessons learned

prior to finalizing the plan. You rec

Questions # 90:

Scenario:

Please read this scenario prior to answering the question

The ABC company is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to " leverage the synergies " that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business.

The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture. The company has selected TOGAF 9 as the basis for its Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario

You are serving as the Chief Architect.

You have been asked to recommend the approach to take in the Preliminary Phase to ensure that the Corporate Board ' s concern is addressed.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You evaluate the implications of the Board ' s concern in terms of regulatory and security policy requirements. You then update the company security policy to reflect the concern, ensuring that this policy is communicated across the organization.You allocate a security architecture team to ensure that security considerations are included in ongoing architecture planning. You then assess the security implications and agreements within the co

B.

You start by clarifying the intent that the Board has for raising this concern. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture.

C.

You evaluate the implications of the Board ' s concern in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the Board ' s concern. You allocate a security architect to oversee the implementation of the solution in the ERP system that is being dev

D.

You evaluate the implications of the Board ' s concern by examining the potential impacts on business goals and objectives. Based on your understanding, you then update the current company security policy to include an emphasis on the Board ' s concern.In addition, you allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.