Questions # 11:

During a coordination meeting, project leads ask for a report showing only active clashes between mechanical systems and structural framing in patient-room zones, following the approved clash matrix.

What is the most effective way to provide this report using Model Coordination?

Options:

A.

Create a custom View from the published models, then export the filtered clash-list results.

B.

Ask each discipline to review its own clash results and report any critical issues from its perspective.

C.

Export all clash results to a spreadsheet and manually filter by trade and zone.

D.

Assign all relevant clashes to mechanical and structural teams using the Issues tool.

Questions # 12:

A contractor has requested the Architectural Revit model for a design-bid-build project to help with their fabrication drawings. The contractor understands and agrees that construction documents will govern in case of discrepancies.

How should the BIM Manager proceed?

Options:

A.

Add the contractor to the Autodesk Forma project for model access given their understanding.

B.

Copy the model file and send it as soon as possible.

C.

Verify that the contractor has signed a digital content release form before sending the model.

D.

Export the sheets to DWG format and send those files.

Questions # 13:

A firm-wide Revit template has an advanced setup of views preset on sheets. A renovation project has a linked as-built model with levels that do not align with levels from the model template.

What method should a BIM manager use to update the levels and create grids in sync with the resource model, without requiring extensive reworking of the preset sheets?

Options:

A.

Align model levels to the linked levels and use Copy/Monitor to duplicate the linked grids.

B.

Create a Scope Box around the linked model and assign it to the template levels and grids.

C.

Delete the template’s levels and use Copy/Monitor to duplicate the linked levels and grids.

D.

Customize a View Template to hide the template levels and only show the linked levels.

Questions # 14:

What setting should be defined in the Family Template for Mechanical Equipment families intended for use in projects in specific countries?

Options:

A.

Object Styles set to the country’s official language.

B.

All parameters set to Instance.

C.

Project Location set to the intended country.

D.

Units set to the intended country’s standard format.

Questions # 15:

A museum project anticipating generative iterations is being designed by a team working across multiple time zones under a tight schedule. The client hosts weekly meetings to review various façade options, document sustainability goals, and evaluate numerous energy analyses.

What project-specific training should the design technology team provide to prepare the team for client meetings and ensure successful project execution?

Options:

A.

AutoCAD, Autodesk Forma, generative design.

B.

Generative design, AutoCAD, Civil 3D.

C.

Forma Site Design, generative design, Autodesk Forma.

D.

Sustainability certification, Revit, Forma Site Design.

Questions # 16:

A design team is distributing models to a construction team’s coordinator, who reports that the various models are not aligned to each other when linked into the coordination environment.

What step should the design team’s lead BIM manager take to resolve the positioning issue?

Options:

A.

Reset coordinates and advise the coordinator to link all models by Internal Origin to Internal Origin.

B.

Publish coordinates from the Main Model out to all linked consumed consultant files.

C.

Report coordinates to provide the coordinator with the desired positioning of each model for them to reposition.

D.

Advise consultants to acquire coordinates from the primary design team’s model and resubmit updated models.

Questions # 17:

The BIM Execution Plan (BEP) has just been completed for a new project. To ensure all multidisciplinary team members review and understand their roles and responsibilities, what is the most effective way to distribute the BEP before the project starts and ensure it remains accessible to everyone throughout the project?

Options:

A.

Include the BEP as part of the project contract and distribute it at project kickoff.

B.

Conduct a mandatory training session to review the BEP and archive it as official once approved by all disciplines.

C.

Upload the BEP to Autodesk Forma in a shared folder location to serve as a live copy.

D.

Email the BEP to all team members and request that they sign and return it as confirmation of review and agreement.

Questions # 18:

What setting should be defined in the Family Template for Mechanical Equipment families intended for use in projects in specific countries?

Options:

A.

Object Styles set to the country’s official language.

B.

All parameters set to Instance.

C.

Project Location set to the intended country.

D.

Units set to the intended country’s standard format.

Questions # 19:

A BIM manager is preparing to onboard a group of subcontractors into Autodesk Forma for a large healthcare project. These subcontractors need access to a limited set of model files related only to interior partitions, but should not be able to view or modify structural, MEP, or scheduling content.

What two actions should the BIM manager take to manage data security in this scenario? (Select two.)

Options:

A.

Create and share a Package with specific set-up content.

B.

Provide access to the entire model set but watermark any non-applicable content.

C.

Assign full project access and ask team leads to verbally explain access limitations.

D.

Hide coordination issues from the subcontractors to limit liability.

E.

Assign role-based permissions and folder-level access aligned with the subcontractors’ scope.

Questions # 20:

A regional user group raised awareness about a third-party add-on tool that enables a team to establish thresholds for model warnings. In addition, it automates suppressing warnings deemed negligible to a specific project.

Which two data points should a BIM manager gather to build a business case to have the tool approved for use across the firm? (Select two.)

Options:

A.

The cost per user multiplied by the number of entire office staff, including the cost of time to implement and train on the tool.

B.

How many of the firm’s competitors are already using the tool.

C.

The language that available training materials on the tool are in.

D.

The reliability of the tool creator and the time to install, test, and create training materials on the tool.

E.

The relevant user group, the projected cost to supply the group, and the anticipated time savings and/or risk mitigation that the tool would provide.