Questions # 21:

Screwdriver Ltd runs a Lean manufacturing process and has recently sequenced its supply chain. It discovered that there is an average two-day delay between the completion of task 1 and task 2. What type of cost is this?

Options:

A.

interchange cost

B.

direct cost

C.

indirect cost

D.

dependency cost

Questions # 22:

Ian is a Project Manager for a large construction project involving the building of a new hospital. A complex supply network is involved which includes the use of several subcontractors. Which of the following would be thebest methodfor dealing with subcontractors for this project?

Options:

A.

involve subcontractors early on in the planning stage

B.

focus on price and have a transactional relationship with subcontractors

C.

ensure all communication with subcontractors is via the tier-one suppliers

D.

closely manage subcontractors by using KPIs and holding regular meetings with them

Questions # 23:

Yes Ltd is a consultancy organisation running many projects simultaneously. Fiona, the CEO, claims that all projects should use project management software. Is this correct?

Options:

A.

yes – software will ensure projects are delivered to timescales and budgets

B.

yes – all projects require the use of software to track data

C.

no – the use of software may not be required for smaller projects

D.

no – software should never be used as a project management tool

Questions # 24:

Participative Evolution is a change model which requires which of the following in order to be effective?

Options:

A.

tight timescales

B.

political capital

C.

consultative style of leadership

D.

large budget

Questions # 25:

Which of the following situations would be considered a‘soft’problem?

Options:

A.

a technical problem with a system

B.

a shift in culture leading to changing buying habits of customers

C.

a delivery of vital materials has been lost in transit

D.

a manager has been found guilty of bribery

Questions # 26:

Which of the following is arisk in the supply chainwhich could affect the delivery of a project?

Options:

A.

project exceeds budget

B.

late delivery of items leading to delays

C.

vital project team members leave the organisation

D.

project scope increase