Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75

Pass the Construction Specifications Institute CDT Certification CDT Questions and answers with Dumpstech

Exam CDT Premium Access

View all detail and faqs for the CDT exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 2 out of 4 pages
Viewing questions 11-20 out of questions
Questions # 11:

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

Options:

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Questions # 12:

Lump sum, unit price, and cost-plus-fee are examples of what?

Options:

A.

Delivery method

B.

Bonding system

C.

Basis of payment

D.

Cost estimate

Questions # 13:

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

Options:

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Questions # 14:

Which of the following is an example of quality assurance?

Options:

A.

Performing compaction testing

B.

Field observations

C.

Validating quantities for payment

D.

Scheduling and sequencing of the work

Questions # 15:

What is the term used to describe the time it takes to procure an item on site?

Options:

A.

Estimated time of arrival

B.

Procurement time

C.

Lead time

D.

Manufacturing time

Questions # 16:

In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?

Options:

A.

Surety, on contractor's behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Questions # 17:

Which of the following establishes a baseline from which deviations are identified?

Options:

A.

General requirements

B.

Supplementary conditions

C.

Project manual

D.

General conditions

Questions # 18:

Which term or word is appropriate to use in specification text?

Options:

A.

Any

B.

As per

C.

As required

D.

Work

Questions # 19:

Procedural requirements for alternates, project meetings, and submittals belong where?

Options:

A.

Divisions 02-49

B.

The general conditions

C.

The supplementary conditions

D.

Division 01

Questions # 20:

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

Options:

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Viewing page 2 out of 4 pages
Viewing questions 11-20 out of questions