Big Black FridaySale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70
Pass the Construction Specifications Institute CDT Certification CDT Questions and answers with Dumpstech
In which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?
Options:
Project Conception phase
Schematic Design phase
Design Development phase
Construction Documents phase
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s project delivery model, the level of development of specifications increases as the project moves through the design phases:
Project Conception – programming, needs assessment, feasibility; little or no formal specifications.
Schematic Design (SD) – conceptual design, basic systems and relationships; CSI now emphasizes Preliminary Project Descriptions (PPDs) as early, performance-oriented spec tools at this stage.
Design Development (DD) – selection and refinement of specific systems and assemblies; this is where outline specifications or expanded PPDs are used as a structured checklist for developing detailed requirements.
Construction Documents (CD) – full, coordinated section-by-section specifications in MasterFormat order, fully detailed to support bidding and construction.
CSI’s Construction Specifications Practice and CDT materials explain that outline specifications (or expanded PPDs) in the Design Development phase play a key role as a checklist and coordination tool. They:
List major assemblies, systems, and products by specification section.
Identify key performance and quality requirements in a concise format.
Help ensure that nothing is overlooked when moving into full specification writing in the Construction Documents phase.
Support coordination between disciplines (architectural, structural, MEP, etc.) by providing a common list of systems and materials.
Therefore, the phase where “outline specifications are created in order to be used as a checklist for further development of the project documents” is the Design Development phase (Option C).
Why the others are not the best fit:
A. Project Conception phaseAt this early stage, work is focused on needs, scope, feasibility, and budgeting. Specifications are generally not yet developed to the “outline” level; instead, information is more conceptual and programmatic.
B. Schematic Design phaseCSI increasingly promotes Preliminary Project Descriptions (PPDs) during Schematic Design, which are even higher-level and more performance-based than traditional outline specs. While some offices may start outline specs during SD, CSI’s standardized view places the checklist-style outline specifications more firmly in Design Development, when system choices are better defined.
D. Construction Documents phaseBy this phase, specifications are typically developed into full, detailed sections (Part 1–General, Part 2–Products, Part 3–Execution) rather than simple outline checklists. The outline specs or expanded PPDs created earlier in DD have already served their purpose in guiding the development of these full specifications and coordinated drawings.
CSI reference concepts:
CSI Project Delivery Practice Guide – chapters describing the design phases and the evolution from PPDs/outline specifications to full specifications.
CSI Construction Specifications Practice Guide – sections on preliminary specifying, PPDFormat, and the role of outline specifications during the Design Development phase.
During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?
Options:
Solicitation
Instructions for Procurement
Instructions to Bidders
Request for Scope of Work
In CSI and CDT terminology, the process of reaching out to potential or prequalified bidders to obtain bids or proposals is called “solicitation.”
The procurement (bidding) phase includes preparing procurement documents and then soliciting bids or proposals from interested or qualified firms.
“Solicitation” covers all methods used to notify and invite participation: advertisements, invitations to bid, requests for proposals (RFPs), and notices to prequalified bidders.
CSI’s Project Delivery Practice Guide and CDT study materials describe the sequence in the procurement stage roughly as:
Preparation of procurement documents (including Instructions to Bidders/Offerors, bid forms, proposed contract forms, etc.).
Solicitation of bids or proposals – announcement or direct issuance to prospective bidders.
Receipt, opening, and evaluation of bids/proposals.
Recommendation and award of contract.
Within that structure, “solicitation” is clearly identified as the step where the owner/AE issues the invitation to bid or request for proposals. The other answer choices refer to documents or requests that are part of the process, but not the process itself:
B. Instructions for Procurement – The CDT/CSI terminology is usually “Instructions to Bidders” or “Instructions to Offerors,” which are sections within the procurement documents explaining how to submit bids (time, place, format, required forms, etc.). They are not the act of announcing or inviting; they are a part of the documents used once solicitation has begun.
C. Instructions to Bidders – This is a specific document or section that sets the rules for bidding (bid security, withdrawal of bids, opening procedures, etc.). It is not the overall process of broadcasting the opportunity; instead it governs bidder behavior after solicitation has occurred.
D. Request for Scope of Work – This is not a standard CSI/CDT term. Scope of work is normally defined in the drawings, specifications, and sometimes in a statement of work, but “request for scope of work” is not used as the formal label for the invitation stage.
Because the question asks specifically for “the process of notifying prospective or qualified bidders requesting proposals for a specific project or an invitation to bid,” the correct CSI-aligned term is “Solicitation” (Option A).
Relevant CSI references (no URLs):
CSI Project Delivery Practice Guide – Procurement phase and terminology for solicitation of bids/proposals.
CSI Construction Specifications Practice Guide – Sections on procurement and bidding documents.
CSI CDT Body of Knowledge – Topic: Procurement (solicitation and receipt of bids/proposals).
What can value analysis be used for?
Options:
To provide the owner with the lowest construction cost.
To enhance project value or reduce initial or long-term cost.
A phase for future work to allow higher quality items up front.
To change the perceived value by owner and stakeholder.
CSI uses the term value analysis or value engineering to describe a structured, function-oriented process that examines the relationship between:
The functions a building element or system must perform, and
The cost of achieving those functions
The objective is to improve value, which can mean:
Reducing initial cost without reducing required performance or quality
Reducing life-cycle cost (operation, maintenance, replacement)
Improving performance, quality, durability, or maintainability for a similar cost
Therefore, value analysis can be used:
“To enhance project value or reduce initial or long-term cost.” (Option B)
CSI stresses that value analysis is not simply “cheapening” the project; it is a disciplined decision-making process that balances cost and function to achieve the best overall value for the owner.
Why the other options are not correct in CSI terms:
A. To provide the owner with the lowest construction cost.The lowest first cost is not the sole or primary goal under CSI’s view. An excessively low first cost may sacrifice performance or significantly increase operation and maintenance costs. Value analysis focuses on best value, not just cheapest construction.
C. A phase for future work to allow higher quality items up front.Value analysis is a process or technique, not merely a “phase for future work.” It also does not inherently mean you always choose higher quality up front; sometimes it leads to lower initial cost, sometimes to better performance, sometimes a balance.
D. To change the perceived value by owner and stakeholder.While owner and stakeholder perception matters, CSI presents value analysis as a technical, function-and-cost-based method, not just a way to change perceptions. The goal is objective improvement of value, not merely altering how the project is perceived.
Key CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – sections on Value Analysis/Value Engineering in design and preconstruction phases.
CSI CDT Body of Knowledge – topics on cost, value, life-cycle thinking, and decision-making.
CSI-related discussions of life-cycle cost and value in project decision processes.
When is decommissioning required for a facility?
Options:
When the entire building is going to be demolished
When the facility is no longer needed for operations
When the facility will not be used again in the future
When the building changes owners
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s description of the facility life cycle, the last phase is decommissioning. This phase occurs when a facility is taken out of service because it is no longer needed for its original operations, has reached the end of its useful life, or is being prepared for conversion to a different use. The emphasis is on the facility no longer being required for its intended operations, not strictly on demolition or permanent abandonment.
Decommissioning tasks can include: removing or securing systems, handling hazardous materials, salvaging components, planning for demolition, or preparing the facility for a different use.
Because decommissioning can precede demolition, adaptive reuse, or other end-of-life actions, it is triggered when the facility is no longer needed for operations.
Option B captures this definition accurately.
Options A and C are too narrow: demolition or permanent disuse are possible outcomes of decommissioning but not the only reasons it is required. Option D (change of ownership) does not automatically require decommissioning; a facility can continue operating normally under a new owner.
Relevant CSI references (no links):
CSI Project Delivery Practice Guide – Facility Life Cycle chapter (discussion of operations, maintenance, and decommissioning).
CSI CDT Body of Knowledge – overview of project phases including decommissioning.
When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?
Options:
The architect/engineer’s projected operating costs
The construction manager’s life cycle analysis
The estimator’s preliminary project description
The facility manager’s historical record of actual costs
CSI’s project-delivery and facility-management perspective emphasizes that O&M budgeting should be grounded in real, documented performance and cost history wherever possible. The facility manager is the team member who typically maintains:
Utility bills
Maintenance contracts and work orders
Repair and replacement histories
Staff, labor, and consumables costs
These form a historical record of actual O&M costs, which provides the most reliable basis for forecasting future O&M budgets.
Technical guidance on O&M cost analysis similarly stresses that:
Agencies “should maintain O&M cost records” that document baseline costs.
When defining an O&M cost baseline, it is recommended to use as much historical data as possible, and that historic O&M costs and actual site data should be used wherever possible.
Research on O&M budgeting practice has found that historical-based budgeting predominates among budgeting bases used in real facilities.
That is exactly what Option D describes: the facility manager’s historical record of actual costs is the correct and most defensible basis for making O&M budget decisions.
Why the others are less appropriate from a CSI/CDT standpoint:
A. Architect/engineer’s projected operating costs – A/E projections can be useful at early planning stages, but they are estimates, not verified costs. Once a facility has operating history, the A/E’s projections are secondary to actual cost data.
B. Construction manager’s life cycle analysis – Life-cycle cost analyses are valuable for choosing systems and strategies, but they are models and assumptions, not the primary budget baseline once real cost data exist.
C. Estimator’s preliminary project description – A Preliminary Project Description (PPD) is a design-stage estimating and scoping tool, not an operating-cost record. It has no direct tie to actual O&M performance.
Therefore, under CSI-aligned practice, the facility manager’s historical record of actual costs (Option D) is the correct basis.
Core CSI-aligned references for this question (no URLs):
CSI Project Delivery Practice Guide – chapters on facility management and life-cycle considerations.
DOE/FEMP guidance on O&M baselines and cost savings, stressing use of historic O&M cost data and actual site data.
Research on O&M budgeting showing predominance of historical-based budgeting.
Who is responsible for job site security?
Options:
Owner
Architect/engineer
Contractor
Construction manager
Under CSI’s project delivery framework and the typical General Conditions of the Contract, the contractor has primary responsibility for:
The means, methods, techniques, sequences, and procedures of construction.
Job site safety and security, including protection of workers, the public, and the work itself.
Controlling access to the site, securing materials and equipment, and complying with safety laws and regulations.
CSI’s CDT materials summarize the allocation of responsibilities this way (paraphrased):
The owner is responsible for providing information, funding, and overall project requirements; the owner does not direct day-to-day site operations or security.
The architect/engineer is responsible for design and contract administration functions such as reviewing submittals, certifying payments, and evaluating change requests—not for job site security or safety control.
The contractor (or construction manager acting as contractor, where applicable) is the party who controls the site and is therefore responsible for job site safety and security.
Even when a construction manager is involved (Option D), CSI and standard general conditions distinguish between a CM as advisor (who advises the owner) and a CM as constructor (who is essentially the contractor). For the exam-style question as written, “contractor” is the single correct generic answer for who is responsible for job site security.
Why the other options are not correct:
A. Owner – The owner does not direct means and methods or daily site activities; shifting site security responsibility to the owner would contradict the usual conditions of the contract.
B. Architect/engineer – The A/E does not control the job site and is not responsible for job site safety/security; this is a repeated CDT exam emphasis to avoid misallocating liability.
D. Construction manager – Only in specific project delivery methods where the CM is also the constructor (CM-at-Risk) does this role overlap with the contractor. The question’s general form points to the contractor as the standard answer in CSI’s framework.
Therefore, in accordance with CSI’s explanation of roles and responsibilities under standard conditions of the contract, the contractor is responsible for job site security, making Option C correct.
Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?
Options:
Conformed set
Record set
Change order log
Request for information documents
CSI describes that during the construction phase, the contractor is responsible for maintaining a continuously updated set of record documents (often called record drawings or as-built drawings). These are a marked-up set of the contract drawings (and sometimes specifications) showing actual field conditions, including:
Changes in dimensions or locations of foundations and structural elements (e.g., pier depths).
Exact locations of underground and concealed utilities.
Adjustments made during construction that are not fully captured in formal design revisions.
Any other deviations between the original design intent and the actual constructed work that will affect future maintenance, alterations, or operations.
CSI’s guidance is that these markups are maintained continuously on site by the contractor and then turned over at closeout as part of the project record.
This is exactly what Option B – Record set refers to: a set of documents updated to reflect the actual constructed conditions.
Why the other options are incorrect:
A. Conformed setA conformed set is the contract documents updated by the design professional to incorporate all addenda and certain pre-award changes, forming a clean set for construction. It is not the running field record of what was actually built; it’s a “clean” version of what was contracted, not what was constructed.
C. Change order logThe change order log tracks formal contract modifications (change orders) – values, dates, brief descriptions. It does not typically contain detailed field information such as exact pier depths and utility locations. Those details belong on the record drawings/record set.
D. Request for information documentsRFIs (requests for information) are used for clarifications and questions during construction. While they may trigger changes or clarifications, RFIs are not the place where the contractor maintains the running graphic record of actual field conditions. The results of RFIs that change the work must still be reflected on the record set.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – Construction Phase, “Record Documents / As-Built Drawings.”
CSI Construction Specifications Practice Guide – Division 01 sections on “Project Record Documents” and “Closeout Submittals.”
CDT Body of Knowledge – Construction Phase responsibilities of the contractor and record documentation.
Who has the right to stop the work if hazardous materials are encountered during the construction?
Options:
Architect/engineer
Contractor
Stakeholders
Facility manager
Under standard conditions of the contract used in CDT (e.g., AIA A201 as referenced by CSI), when hazardous materials or unsafe conditions are encountered:
The Contractor is required to stop work in the affected area and notify the Owner and Architect/Engineer.
The Contractor must not proceed until the hazardous condition has been evaluated and remedied by the Owner with qualified professionals.
CSI’s project delivery materials emphasize that the contractor is responsible for means, methods, and safety of construction operations. That includes the authority—indeed the obligation—to stop work where hazardous substances or conditions present an imminent danger to workers.
Why the others are incorrect:
A. Architect/engineer – The A/E can recommend suspension of work for nonconforming work or other reasons, but the specific duty and right to stop work because of hazardous conditions in the field lies with the Contractor under typical general conditions.
C. Stakeholders – This is a generic term, not a contract party with defined authority in CSI’s framework.
D. Facility manager – The facility manager may be involved if the existing facility is affected, but is not the contract party empowered in the construction contract to stop the contractor’s work.
Relevant CSI references (no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase responsibilities and safety.
CSI CDT Body of Knowledge – discussion of contractor responsibilities and hazardous materials clauses in standard general conditions.
What could a reference standard specification be based upon?
Options:
Project manual for similar project
Design intent
Trade association standard
Manufacturer's specification section
CSI identifies several types of specifications, including:
Descriptive specifications – describe materials and methods in detail.
Performance specifications – describe required results and performance criteria.
Proprietary specifications – designate specific products or manufacturers.
Reference standard specifications – define requirements by citing recognized industry standards rather than repeating all technical details.
A reference standard specification works by referring to standards issued by organizations such as:
Trade associations (e.g., industry associations),
Standards organizations (e.g., ASTM, ANSI, ISO),
Other recognized bodies that publish consensus technical standards.
The specification then simply states that materials, products, or work must comply with the named standard. This reduces repetition and promotes consistency and clarity.
Therefore, a proper basis for a reference standard specification is a trade association standard, which is Option C.
Why the other options are incorrect:
A. Project manual for similar projectPrevious project manuals may be informal references for the specifier, but they are not recognized standards. A reference standard specification must refer to a published technical standard, not another project’s contract documents.
B. Design intentDesign intent is expressed more directly in performance or descriptive specifications, not in reference standard form. Reference standards rely on external, recognized standards, not internal design intent statements alone.
D. Manufacturer's specification sectionReferring to a specific manufacturer’s literature or section is characteristic of a proprietary specification, not a reference standard specification. Reference standards must be based on independent, consensus-based standards, not one manufacturer’s materials.
Key CSI Reference Titles (no links):
CSI Construction Specifications Practice Guide – Types of specifications, including reference standard specifications and their proper use.
CSI Project Delivery Practice Guide – Relationship of specifications to industry standards.
CDT Body of Knowledge – “Specification Types and Methods of Specifying.”
What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?
Options:
Schematic programming
Site selection
Due diligence investigation
Master planning
In CSI’s description of the project conception and pre-design phases, the owner has a responsibility to determine whether a proposed project is feasible and appropriate before moving into full design. One of the key tools for this is a due diligence investigation.
CSI characterizes due diligence as including, for example:
Reviewing legal, zoning, and regulatory constraints.
Evaluating financial feasibility and the owner’s available resources or funding mechanisms.
Considering market conditions, potential users, and long-term operational costs.
Assessing social, environmental, and community impacts (traffic, neighborhood character, environmental effects, required approvals).
Through this activity, the owner can decide whether to:
Proceed with the project as envisioned,
Modify scope, location, or timing, or
Abandon the project if it is not viable.
This aligns directly with Option C – Due diligence investigation, which is about assessing viability, finances, and broader impacts.
Why the other options are less appropriate:
A. Schematic programmingCSI separates programming (defining needs and requirements) and schematic design (early design). The term “schematic programming” is not a standard CSI term. Programming helps define needs but is only one part; due diligence focuses more broadly on viability, finance, and external impacts.
B. Site selectionSite selection is important, but it is one component within a broader due diligence process. It does not, by itself, fully address financial feasibility or community impact; those are evaluated in the larger due diligence/feasibility effort.
D. Master planningMaster planning typically addresses long-range development of a site, campus, or area (phasing, land use, circulation, infrastructure). While it may touch community impacts, it is broader and more strategic. The question specifically targets an activity to assess viability, financial resources, and community impact for a specific project decision—that is due diligence.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – Project Conception and Predesign, Owner’s due diligence and feasibility studies.
CSI Construction Specifications Practice Guide – Owner’s responsibilities prior to design and procurement.
CDT Body of Knowledge – “Owner’s Project Initiation, Feasibility, and Due Diligence.”