Which two statements describe N+1 redundancy?

Options:

A.

It provides spare capacity when one required unit becomes unavailable.

B.

It includes required units plus one additional backup unit installed.

C.

It includes required units without additional capacity for component failures.

D.

It provides independent capacity sets that each support full load.

Questions # 12:

A data center facility employee notices an alarm and plans to change equipment.

What action must occur before the change?

Options:

A.

Confirm current equipment status before reporting the condition to the designated lead.

B.

Review recent alarm trends before reporting the condition to the designated lead.

C.

Report alarm details to the designated lead before changing affected equipment.

D.

Consult approved procedures before reporting the condition to the designated lead.

Questions # 13:

How do environmental monitoring and cooling redundancy work together during a cooling issue?

Options:

A.

Monitoring detects abnormal conditions while redundancy directs technicians toward specific repairs.

B.

Monitoring detects operational conditions while redundancy adjusts cooling equipment settings automatically.

C.

Monitoring detects temperature trends while redundancy increases cooling demand during failures.

D.

Monitoring detects abnormal conditions while redundancy provides response time during failures.

Questions # 14:

If a new alarm appears after earlier service work, what should be reviewed first to reduce guesswork during escalation?

Options:

A.

New work order created while referencing earlier maintenance records.

B.

Current equipment list and prior service history.

C.

Most recent room-average temperature and affected equipment details.

D.

Work-order history and maintenance log for the affected equipment.

Questions # 15:

Which two conditions can indicate reduced water-based cooling?

Options:

A.

Increased pump volume

B.

Stable chilled-water temperatures, combined with increased UV

C.

Abnormal plant-system alarms

D.

Rising rack inlet temperatures

Viewing page 2 out of 2 pages
Viewing questions 11-20 out of questions