Questions # 31:

Which of the below is not a critical organizational element?

Options:

A.

Delivery mechanism for change

B.

Recruitment Policy

C.

Business as usual

D.

Corporate strategy

Questions # 32:

Which of following is NOT part of delivering the capability?

Options:

A.

Start Projects

B.

Governance: Manage and control delivery

C.

Align projects with benefits realization

D.

Gateway reviews

Questions # 33:

The programme is in the ‘deliver the capabilities’ process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.

Which theme is MOST relevant to this situation, and why?

Options:

A.

Decisions, because the programme manager is responding to possible delays to the training courses affecting programme benefits

B.

Decisions, because the problem with the delayed training courses is causing a delay to delivery of the programme benefits

C.

Justification, because the delays to the training courses could impact how quickly the reduced costs are realized

D.

Justification, because further delays to the training courses will start to impact programme costs, affecting the business case

Questions # 34:

Which one of below options is the delivery mechanism for 'stakeholder engagement'?

Options:

A.

Information management plan

B.

Programme communications plan

C.

Benefit profiles

D.

Resource management plan

Questions # 35:

Select the best option defined by following sentence: 'Action of carrying out the coordinated organization, direction and implementation of dossier of projects and transformation activities to achieve desired outcomes'

Options:

A.

Project Management

B.

Programme Management

C.

Portfolio Management

D.

Organizational Management

Questions # 36:

The programme is in the ‘close the programme' process. All the projects have been successfully completed, and the capabilities have been delivered. However, some of the new sales roles are still to be recruited in order to deliver increased sales. The programme manager has passed the management of this remaining work to the HR Director.

Is this an appropriate action for the programme manager to take, and why?

Options:

A.

Yes, because the remaining recruitment should be handed to the HR Director to ensure that the benefits are realized

B.

Yes, because the impact of closure on the HR Director needs to be understood and managed well

C.

No, because programme information should be up-to-date and archived before the programme can be formally closed

D.

No, because the SRO should be responsible for disbanding the programme team and closing the programme

Questions # 37:

Which document is created from Programme mandate and works as input for Business Case?

Options:

A.

Programme preparation plan

B.

Blueprint

C.

Programme Brief

D.

Programme management plan

Questions # 38:

The programme is in the middle of Tranche 2 and a new SRO has been appointed. In order to understand the current status of the programme, the SRO has asked for a health check to be carried out. The health check was not in the assurance plan, and there is no budget available to pay for an external auditor. As a result, the programme manager has agreed with the SRO that a senior member of the portfolio office, who is acting as the programme office lead, should complete the health check instead.

How well does this action by the programme manager apply the ‘assurance' theme, and why?

Options:

A.

It applies it well, because the programme office lead has the skills to carry out a health check to assess progress against plans and identify areas of the programme that need attention

B.

It applies it well, because a health check should give the SRO reassurance that the programme is being run in a compliant way

C.

It applies it poorly, because the programme board should undertake health checks on behalf of the SRO to identify areas for improvement

D.

It applies it poorly, because assurance activities should have been planned in the plan progressive delivery' process and remain unchanged throughout the programme

Questions # 39:

Which of the following statements is NOT TRUE?

Options:

A.

The SRO is accountable for confirming Programme Mandate.

B.

The SRO is accountable for the Programme Brief.

C.

The Programme Manager is responsible for the Vision Statement.

D.

The Programme Manager is responsible for the Blueprint.