Questions # 1:

Which of the following is a KEY attribute for a Programme Manager?

Options:

A.

Have ongoing operational responsibilities within their business area

B.

Change management skills

C.

A good knowledge of project management approaches

D.

Have access to key stakeholders

Questions # 2:

The programme is halfway through the first tranche. The CRO has contacted the programme manager with exciting news. They have been shown a new piece of technology which makes it easier and cheaper to service and maintain smart meters. They think that it might be possible to add this technology to future smart water meter installations without much additional cost. The programme manager has added this to the risk register.

Is this an appropriate application of the design' theme, and why?

Options:

A.

Yes, because if smart meter installations include this technology then future maintenance costs could be reduced

B.

Yes, because changing the existing installation plan could bring uncertainty to the programme and should be avoided

C.

No, because reduced maintenance costs should be added to the benefits map as a new benefit of the programme

D.

No, because the possibility of reducing maintenance costs should be treated as an issue and action taken immediately

Questions # 3:

The programme is in the ‘deliver the capabilities’ process in Tranche 1. The Employment Contracts Project needs to identify the skills and qualifications for call centre staff. The Call Centre Manager is concerned that the delivery of the web-based portal, being delivered in Tranche 2, will affect the skills required. They are worried that this may lead to some considerable rework during Tranche 2.

Which role should be responsible for making sure that the Call Centre Manager’s concerns are properly managed?

Options:

A.

Sponsoring group members

B.

Senior responsible owner

C.

Programme manager

D.

Programme office lead

Questions # 4:

Which of the following defines Dis-benefit?

Options:

A.

Measurable improvement resulting from outcome perceived as an advantage

B.

A scenario that may bring profit or loss to programme

C.

Unplanned scenario that has happened and needs management intervention to reduce negative impact

D.

Measurable decline resulting from outcome perceived as negative

Questions # 5:

The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.

Is this recommendation an appropriate application of the ‘decisions' theme, and why?

Options:

A.

Yes, because the proposed option should gain the CEO’s full support

B.

Yes, because providing a clear recommendation should bring pace and value

C.

No, because there are security risks identified with the option proposed

D.

No, because a ‘do-nothing’ option and at least two others should be provided

Questions # 6:

Which of the following is a programme management principle?

Options:

A.

Quality and assurance management

B.

Remaining aligned with corporate strategy

C.

Leadership and stakeholder management

D.

Realizing the benefits

Questions # 7:

Which of following is output of 'Identifying the programme'?

Options:

A.

Programme Mandate

B.

Appointment of programme board and SRO

C.

Business Case

D.

Benefit profiles

Questions # 8:

As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?

Options:

A.

Keep informed, active consultation, maintain interest

B.

Active consultation, keep informed, maintain interest

C.

Keep informed, maintain interest, active consultation

D.

Maintain interest, active consultation, keep informed

Questions # 9:

In Managing the Tranches, which role is responsible for preparing for the next tranche?

Options:

A.

The Programme Manager

B.

The Programme Board

C.

The Benefits Realization Manager

D.

The Programme Office

Questions # 10:

Which of following documents are parts of governance themes?

Options:

A.

Blueprint, Vision, Quality management strategy

B.

Business Case, Programme mandate

C.

Blueprint, Requirement Specification

D.

System and product specification