Questions # 1:

During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown’s ‘green town’ status.

During which ‘initiating a project’ activity should this workshop take place?

Options:

A.

Agree the tailoring requirements

B.

Agree the management approaches

C.

Prepare the project plan

D.

Prepare the full business case

Questions # 2:

The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because restricting the CTO’s involvement would protect the project’s reputation from untested proposals

B.

Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty

C.

No, because the project manager should record the technological concerns only as risks requiring formal responses

D.

No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem

Questions # 3:

A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because the legislation may affect the resources available to deliver the project

B.

Yes, because external events must be managed outside the project’s agreed controls

C.

No, because legislation should be recorded after its full effect on delivery is known

D.

No, because external events are managed by the business rather than by the project team

Questions # 4:

The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.

Does this represent an appropriate application of the ‘business case’ practice, and why?

Options:

A.

Yes, because developing the business case from multiple perspectives – strategic, economic, and commercial – ensures a comprehensive and robust justification for the project investment

B.

Yes, because the project should align its approach to business case development with the City Council’s established procedure, which serves as the equivalent of PRINCE2’s recommended business case lifecycle

C.

No, because the full business case should be developed from an outline business case prepared during the ‘starting up a project’ process, and using a ‘strategic business case’ instead is not compliant with the method

D.

No, because responsibility for developing the full business case for each project in the portfolio lies with the portfolio office, not the project team

Questions # 5:

During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.

Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?

Options:

A.

Business layer

B.

Team manager

C.

Project assurance

D.

Project executive

Questions # 6:

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

Options:

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Questions # 7:

While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.

Is this an appropriate application of the organization practice, and why?

Options:

A.

Yes, because the Mayor may delegate responsibility for appointing the project executive to any senior stakeholder involved in the project

B.

Yes, because the Portfolio Director, as the business layer representative, takes responsibility for appointing the project executive

C.

No, because it is the Mayor, as the senior elected authority, who should personally select and appoint the project executive for a project of this civic significance

D.

No, because the responsibility for commissioning and initiating projects within the LOB portfolio rests with the Head of Portfolio Office, not the Portfolio Director

Questions # 8:

RISK

Here are three items of information relating to the ‘risk’ practice.

In which management product (A–E) should each item be recorded?

Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.

Options:

A.

Risk register

B.

Issue register

C.

Quality management approach

D.

Issue report

E.

Risk management approach

Item 1:

A cracked pane has already been identified and replacement is planned for next week. The project manager records the separate uncertainty that the supplier may miss that future replacement date and delay subsequent work.

Item 2:

The agreed procedure states that the project board and project manager will review all open risks during every end stage assessment.

It

Questions # 9:

Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.

During which ‘managing product delivery’ activity should this be done?

Options:

A.

Notify work package completion

B.

Execute a work package

C.

Evaluate a work package

D.

Accept a work package

Questions # 10:

At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.

Which practice is being applied?

Options:

A.

Business case

B.

Plans

C.

Progress

D.

Quality