75only - Ends in 0d 00h 00m 00s - Coupon code = 75only
Pass the PRINCE2 Certification PRINCE2-7-Practitioner Questions and answers with Dumpstech
Exam PRINCE2-7-Practitioner Premium Access
View all detail and faqs for the PRINCE2-7-Practitioner exam
During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown’s ‘green town’ status.
During which ‘initiating a project’ activity should this workshop take place?
The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.
Is this an appropriate approach to leading successful change, and why?
A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.
Is this an appropriate application of the issues practice, and why?
The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.
Does this represent an appropriate application of the ‘business case’ practice, and why?
During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.
Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?
The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.
Under which heading of the change management approach should this requirement be recorded?
While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.
Is this an appropriate application of the organization practice, and why?
RISK
Here are three items of information relating to the ‘risk’ practice.
In which management product (A–E) should each item be recorded?
Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.
Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.
During which ‘managing product delivery’ activity should this be done?
At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.
Which practice is being applied?