Questions # 11:

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

Options:

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier

Questions # 12:

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

Options:

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Questions # 13:

During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.

Is this an appropriate application of the ‘learn from experience’ principle, and why?

Options:

A.

Yes, because the regular knowledge-sharing sessions provide a structured mechanism for team managers to identify and apply lessons arising during the current stage

B.

Yes, because the subcontractors are expected to contribute lessons from previous construction projects that are directly relevant to the current stage

C.

No, because subcontractors should concentrate on meeting their work package commitments and tolerances rather than attending sessions that take them away from delivery

D.

No, because the Regeneration Manager should gather lessons through individual interviews with team managers and document them formally in a lessons report at the end of the stage

Questions # 14:

In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager. The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.

Is this an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

Options:

A.

Yes, because the principle requires that communication channels between all internal and external project team members remain open and transparent at all times

B.

Yes, because the Heritage Manager needs a clear understanding of what the Heritage Director requires of them and of what they may reasonably expect from the other parties involved

C.

No, because it is the project manager’s responsibility to specify how inspections of historically significant buildings should be planned and executed

D.

No, because the Heritage Director, as senior user, should personally conduct the assurance review of the inspection plans rather than delegating to the Heritage Manager

Questions # 15:

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Questions # 16:

During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.

The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?

Options:

A.

Yes, because evaluation confirms that completed quality activities are recorded and that the current status is understood by the relevant parties

B.

Yes, because the team manager should review the work-package information, report progress for the agreed period, and notify the project manager when a tolerance is forecast to be exceeded

C.

No, because only the project manager may evaluate the status of a work package and decide what it should report

D.

No, because a forecast work-package tolerance breach should be reported directly to the project board in an exception report