Questions # 21:

Which is a benefit of the Lean Startup approach to releasing a product?

Options:

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

Questions # 22:

Which role is responsible for facilitating the Agilometer assessment?

Options:

A.

Project board

B.

Project manager

C.

Team manager

D.

Customer subject matter expert

Questions # 23:

What is a role of personas in the 'business case' practice?

Options:

A.

To group users based on demographic data

B.

To ensure project timelines are met

C.

To identify and articulate specific user benefits

D.

To differentiate between product versions

Questions # 24:

Which BEST describes the senior user role when tailoring the organization theme?

Options:

A.

An ‘agile sponsor’

B.

An ‘executive sponsor’

C.

A ‘coach’

D.

A ‘super product owner’

Questions # 25:

Which principle establishes governance by delegating responsibilities and setting tolerances?

Options:

A.

Ensure continued business justification

B.

Tailor to suit the project

C.

Manage by exception

D.

Focus on products

Questions # 26:

Which statement about velocity is CORRECT?

Options:

A.

It is based on the concept of rationalism

B.

It is shown by the ideal line on a bum-down chart

C.

It describes how much work is getting done

D.

It tracks the time and cost of a timebox

Questions # 27:

What BEST defines embryonic customer requirements?

Options:

A.

‘Fine-grained’ user stories

B.

Epics

C.

Sub-products

D.

Technical stories

Questions # 28:

What is the definition of a timebox?

Options:

A.

A tool to write a requirement in the form of who, what and why

B.

A regular event that looks at how processes can be improved

C.

A description of the rate of progress a team is making

D.

A period where work is carried out to achieve a goal

Questions # 29:

What is an epic?

Options:

A.

A low-level requirement

B.

A fine-grained user story

C.

A detailed feature

D.

A high-level requirement

Questions # 30:

Which statement about the ‘initiating a project’ process is CORRECT?

Options:

A.

The initiation stage plan should form part of the project plan

B.

The impact of frequent releases on quality management should be assessed

C.

The process should take more time than usual for disruptive projects

D.

The project solution should be documented in detail in the project product description