Questions # 1:

In the effort of improving the code quality, Universal Containers (UC) has asked a third-party system integrator to perform some independent code reviews. One piece of the feedback is the development team is seemingly not doing enough negative unit testing.

Which are three usual symptoms of inadequate negative tests? Choose 3 answers

Options:

A.

Developers often have to turn to the debug log for details of the failed Apex executions.

B.

When an Apex batch job runs at a scheduled time, an increased number of Apex execution errors occur over all.

C.

An Apex process runs into an un-handled exception when an HTTP callout has an unexpected status code in the response body.

D.

Developers constantly ask the testers for a screenshot of the error and the exact steps of reproducing the error.

E.

The delivered user interfaces are regularly not meeting the expectations of the business users.

Questions # 2:

Universal Containers (UC) currently uses the org development model and utilizes the Salesforce CLI as the deployment tool. After the feature release artifact file has been tested in a lower sandbox, it is being deployed to the full sandbox for performance testing and production deployment readiness check.

Since quick deployment options are not being used, what is the correct way to deploy the artifact to the full sandbox?

Options:

A.

Authorize to the Full sandbox; Validate with sfdx:source:deploy. On successful validation, deploy with sfdx:mdapi:deploy

B.

Authorize to the Full sandbox org; Validate with sfdx:mdapi:deploy On successful validation, deploy with sfdx:mdapi:deploy

C.

Authorize to the Full sandbox org; Validate with sfdx:source:deploy; On successful validation, deploy with sfdx:source:deploy

D.

Authorize to the Full sandbox org; Validate with sfdx:mdapi:deploy; On successful validation, deploy with sfdx:source:deploy

Questions # 3:

What two things are needed to delete metadata with a deploy() call? Choose 2 answers

Options:

A.

Package.XML file.

B.

The CURRENT API version must be used.

C.

DestructiveChanges.xml file.

D.

PurgeOnDelete option must be set to TRUE.

Questions # 4:

Cloud Kicks (CK) is launching a new sneaker line during the upcoming holiday season and needs to do a thorough batch data testing before Go-Live. CK is using Salesforce unlimited edition.

What two sandbox types should the architect recommend for batch data testing? Choose 2 answers

Options:

A.

Developer sandbox

B.

Developer Pro sandbox

C.

Partial Copy sandbox

D.

Full sandbox

Questions # 5:

Since Universal Containers (UC) has adopted agile methodologies, the CEO is requesting the development teams to deliver more and more work in shorter time frames. The CTO responds by saying the developers are not able to deliver the jobs they are committing to.

What evidence can be gathered in an agile tool to support the CTO ' s claims?

Options:

A.

The definition of done (DoD)

B.

A burndown chart showing team finishes early sprint after sprint

C.

A Kanban board showing there ' s always the maximum allowed amount of work in progress (WIP)

D.

A burndown chart showing the team misses their forecast sprint after sprint

Questions # 6:

Universal Containers has discovered a Servo defect in production. Tens of thousands of records will be created with incorrect data in minutes, producing significant brand damage as a consequence.

The Salesforce administrator has suggested that the defective text field be replaced with a new picklist field directly in production. The page layout will be modified so that the text field is removed and the new picklist field added.

What should the Salesforce architect advise?

Options:

A.

Deny the suggestion and explain to everyone that the risk is too high and the next release window is on the weekend

B.

Pair with the administrator, and review each change as it happens

C.

Call the security team and begin organizing a penetration test.

D.

Explain that only developers are certified to make changes directly in production.

Questions # 7:

Universal Containers (UC) had been using change sets for deploying all of the modifications to its Sales Cloud apps. After multiple business units joined the single Salesforce instance, there is a need to evaluate which development model is the most suitable for UC. The IT management has shown a particular interest in finding out more about the package development model.

As an architect, which two statements can be made to articulate the differences between the change set model and package development model? Choose 2 answers

Options:

A.

In package development, the source of truth is the metadata in the package project, which makes it easy to integrate to a version control System.

B.

A change set can be retrieved from the developer ' s workbench as a package, then pushed into the version control system to achieve the Versioning control.

C.

In change set development, the source of truth is a combination of the metadata already in the environment and the content of your change Set.

D.

In package development, the best practice is to consider the dependencies and build the dependencies into the package so it can be deployed In any other target orgs.

Questions # 8:

Universal Containers has many development teams deploying into a single org. The business is very seasonal and approaching its busiest season. The business owner comes to you asking for your advice about its next major production release.

What best practice should an architect recommend?

Options:

A.

Make declarative changes in production only.

B.

Bypass regression testing for minor changes.

C.

Avoid releasing near peak business periods.

D.

Developers should conduct user acceptance testing.

Questions # 9:

A developer with Universal Containers recently created a flow in the developer sandbox. While working on the flow, the developer deactivated it and made updates multiple times before the flow worked as desired. Now the developer is planning to use a change set to migrate the flow to the QA sandbox.

What two statements should be considered when migrating the flow with change sets? Choose 2 answers

Options:

A.

When a change set with a multiple versioned flow is uploaded, it includes only the active version of the flow.

B.

When a change set with a multiple versioned flow is uploaded, it includes all the versions of the flow.

C.

When a change set with a multiple versioned flow is uploaded, and no active version is available, it includes the most recent inactive version of the flow.

D.

When a change set with a multiple versioned flow is uploaded, and no active version is available, it throws an exception.

Questions # 10:

An architect has been working on a large project for the past 6 months. This project must be live by the end of the current month.

Which two planning techniques should the architect use to ensure all metadata changes deploy smoothly and on time? Choose 2 answers

Options:

A.

Create a new sandbox and perform a test deployment to that environment.

B.

Ensure all code that is being deployed is checked into source control.

C.

Upload a change set from sandbox to production as early as possible.

D.

Validate the final deployment package against production prior to go-live