Summer Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the CIPS Level 4 Diploma in Procurement and Supply L4M3 Questions and answers with Dumpstech
Maximum Score: 1
When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?
A confidentiality clause designed to protect either party
A clause stating how long the service is to be outsourced
A clause stating how long the employees can take for holiday
A contract variation and price adjustment clause
Which of the following are implied terms in sales contracts? Select THREE that apply.
Company A sends a purchase order complete with a set of conditions of contract for the provision of professional services to Company B. Company B responds with an invoice complete with a set of its own conditions of contract. Company A pays the invoice. Whichconditions of contract take legal precedence?
In what way might a contract clause be used to stop the supplier from making unwarranted price increases during the term of the contract?
Which of the following should be applied when measuring frequency of on-time deliveries during a contract period?
Which of the following will be always automatically deemed as a consideration?
One of the important features in the formation of a contract is the need to have a 'consensus ad idem' between the contracting parties. 'Consensus ad idem' can be translated as meaning:
GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.
Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.
Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?
Maximum Score 1
A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a ‘model form contract’?
Which of the following are key features of standard terms and conditions? Select TWO that apply