Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70

Pass the CIPS Level 4 Diploma in Procurement and Supply L4M3 Questions and answers with Dumpstech

Exam L4M3 Premium Access

View all detail and faqs for the L4M3 exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 6 out of 7 pages
Viewing questions 51-60 out of questions
Questions # 51:

Which of the following is the most suitable model contract for car lift manufacturing?

Options:

A.

ITC

B.

FIDIC

C.

IMechE/IET

D.

CIPS

Questions # 52:

Which of the following approaches could a purchasing organisation use to reduce the level of detail in a specification, without increasing the risk of an unsuccessful procurement process?

Increase the use of acronyms and abbreviations

Cross-refer to recognised industry standards

Require tendering suppliers to propose specifications

Provide samples to demonstrate the requirements

Options:

A.

1 and 3 only

B.

2 and 4 only

C.

2 and 3 only

D.

1 and 4 only

Questions # 53:

Which of the following are most likely to be liabilities of suppliers under a guarantee clause?(SelectAny Two)

Options:

A.

TWO that apply

B.

Repair

C.

Decommissioning

D.

Upgrading

E.

Replacement

F.

Installation

Questions # 54:

Maximum Score: 1

John Jameson purchased his new car from Warrington Autos Ltd, a local car dealership. He signed the hire purchase agreement with Car Finance Services Ltd, and made the required three months payment in advance to confirm the purchase and take delivery of the car. On the day of delivery, the car was incorrectly offloaded from the transporter by Vehicle Transport Ltd and the car is a total insurance write off. Which party had title in the vehicle?

Options:

A.

John Jameson

B.

Warrington Autos Ltd

C.

Car Finance Services Ltd

D.

Vehicle Transport Ltd

Questions # 55:

Which of the following is an example of liquidated damages clause?

1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."

2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"

3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."

4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"

Options:

A.

2 and 4 only

B.

1 and 3 only

C.

3 and 4 only

D.

1 and 2 only

Questions # 56:

Which of the following should be specially noticed in market dialogue with suppliers in specification development?

Options:

A.

Both parties must respect confidentiality

B.

The buying organisation must avoid social media at all cost

C.

Market dialogue is banned in the public sector

D.

Market dialogue should only be conducted with well-known supplier

Questions # 57:

Which of the following statement is true about insurance?

Options:

A.

An insurance policy can be mechanism of substance to back up indemnity

B.

The supplier must always pay the insurance premium for goods-in-transit

C.

An insurance policy transfers the legal liabilities from the insured to the insurer

D.

Professional indemnity insurance provides the insured business with financial protection against the liabilities caused by or arising out of the products supplied

Questions # 58:

A procurement professional is preparing a sale & purchase contract of a machinery. Which of the following clauses should be added to the contract? Select TWO that apply

Options:

A.

Supplier selection mechanism

B.

Insurance requirements

C.

Period of hire

D.

Ratio decidendi

E.

Guarantees

Questions # 59:

Which of the following are most likely to be substantive elements of the specification of a truck? Select TWO that apply:

Options:

A.

Guarantee

B.

Foreword

C.

Expected lifespan

D.

Ethics

E.

Abbreviation

Questions # 60:

What are disadvantages of a buyer contracting on the supplier's terms? Select TWO that apply.

Options:

A.

Materials will not be changed without the buyer’s consent

B.

The buyer would not be subject to any indemnity clause obligations

C.

Title to goods may remain with the supplier until payment is received

D.

Goods received late will incur penalties for the supplier

E.

Prices may increase without notification to the buyer

Viewing page 6 out of 7 pages
Viewing questions 51-60 out of questions