Which of the following is the most suitable model contract for car lift manufacturing?
Which of the following approaches could a purchasing organisation use to reduce the level of detail in a specification, without increasing the risk of an unsuccessful procurement process?
Increase the use of acronyms and abbreviations
Cross-refer to recognised industry standards
Require tendering suppliers to propose specifications
Provide samples to demonstrate the requirements
Which of the following are most likely to be liabilities of suppliers under a guarantee clause?(SelectAny Two)
Maximum Score: 1
John Jameson purchased his new car from Warrington Autos Ltd, a local car dealership. He signed the hire purchase agreement with Car Finance Services Ltd, and made the required three months payment in advance to confirm the purchase and take delivery of the car. On the day of delivery, the car was incorrectly offloaded from the transporter by Vehicle Transport Ltd and the car is a total insurance write off. Which party had title in the vehicle?
Which of the following is an example of liquidated damages clause?
1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."
2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"
3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."
4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"
Which of the following should be specially noticed in market dialogue with suppliers in specification development?
Which of the following statement is true about insurance?
A procurement professional is preparing a sale & purchase contract of a machinery. Which of the following clauses should be added to the contract? Select TWO that apply
Which of the following are most likely to be substantive elements of the specification of a truck? Select TWO that apply:
What are disadvantages of a buyer contracting on the supplier's terms? Select TWO that apply.