Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70
Pass the FIDIC Contract Manager CCM Questions and answers with Dumpstech
(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?
Choose all of the correct answers (multiple possibilities).)
(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]
Choose all of the correct answers (multiple possibilities).
Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]
(2 correct answers apply)
(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)
(Under the FIDIC Red Book, which of the following statements are correct? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).)
You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?
A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.
When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)
Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?