Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70

Pass the FIDIC Contract Manager CCM Questions and answers with Dumpstech

Exam CCM Premium Access

View all detail and faqs for the CCM exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 1 out of 4 pages
Viewing questions 1-10 out of questions
Questions # 1:

(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The requirement to submit a revised programme by the Contractor whenever the previous programme is inconsistent with actual progress.

B.

Specifying the programming software that shall be used by the Contractor in preparation of the Programme.

C.

The requirement that any revised programmes to be submitted by the Contractor is to reflect accurately the actual progress of the works.

D.

Submission by the Contractor of a detailed time Programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1.

Questions # 2:

(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)

Options:

A.

You compliment the supervisor and ask him to excavate further and personally deliver the treasure to a university. No extension of time is granted.

B.

You thank the supervisor, secure the Site, instruct guarding measures, inform the Employer and authorities, and issue a Variation to cover the costs of protection measures.

C.

You inform the supervisor that a formal written notice under Sub-Clause 4.24 is required and no further instruction can be given until then.

D.

You instruct the supervisor to cover the finding and resume the Works immediately, and make a determination later.

Questions # 3:

In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]

Choose all of the correct answers (multiple possibilities).

Options:

A.

... the Contractor may send a Notice to the Engineer, that the subject of the Variation was Unforeseeable (having regard to the scope and nature of the Works), hence, the Contractor is not to start implementing the varied work promptly.

B.

... the Contractor is required to commence implementing the varied works and take records of all the details ( ... regarding the details of the varied works executed, expenditures incurred, and impact on progress etc.)

C.

... the Contractor is required to commence implementing the varied works even if it would pose immediate hazard to the safety of public areas surrounding the Site

D.

... the Contractor within 28 days after receiving such instruction shall submit to the Engineer a description of the varied work, a programme for its execution and a proposal for adjustment of the Contract Price.

E.

... the Contractor is not bound to start implementing the varied works right up until the price for the varied works is fully agreed (or determined)

Questions # 4:

Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]

(2 correct answers apply)

Options:

A.

Continuing effect claims shall be noticed in the same way as " normal " claims, within 28 days after the Claiming Party became aware of the event or circumstance.

B.

In case the Employer is the Claiming Party, then he/she is not obliged to submit interim claims.

C.

In case the Contractor is the Claiming Party, when he/she misses to submit even just a single interim claim, then his/her entitlement is lost.

D.

In general, a fully detailed Claim has to be submitted within 84 days after becoming aware of the event giving rise to the claim.

Questions # 5:

(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)

Options:

A.

True

B.

False

Questions # 6:

(Under the FIDIC Red Book, which of the following statements are correct? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).)

Options:

A.

An attempt to reach an amicable settlement is a mandatory requirement before an Engineer ' s ruling can be referred to a DAAB.

B.

A decision by a DAAB is not final and binding on the Parties until it is confirmed by an arbitration award.

C.

The FIDIC Red Book ' s General Conditions specify a standing DAAB.

D.

A DAAB member nominated by one of the Parties must be agreed by the other Party.

E.

If the Employer or the Contractor fails to notify its dissatisfaction with an Engineer ' s ruling within the specified time, the DAAB ' s decision is final and binding.

Questions # 7:

You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?

Options:

A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.

Questions # 8:

A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.

Options:

A.

The Employer should check on the Appendix to Tender, Employer ' s Requirements and / or Particular Conditions. There could very well be specific requirements regarding the language in those. If that is not the case, the language of the Contract determined in Sub-Clause 1.4 and the language of the Operation and Maintained Manuals should in this case be English.

B.

If French is indeed an official second language of the region where the Plant is built, the Contractor is entitled to deliver the documents in French. The usability in terms of language is not described in Sub-Clause 5.7, so the Employer should accept the Operation and Mantained Manuals in French.

C.

Golden Principle no. 1 states: The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, and appropriate to the requirements of the project. In this case this means it is appropriate that the Operation and Maintenance Manuals are in French, as the maintenance is based in France.

D.

As the Contract is written in the English language, Sub-Clause 1.4 dictates that the Operation and Maintenance Manuals should be written in English as well.

Questions # 9:

When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)

Options:

A.

When the Contractor receives full payment certified through the Final Payment Certificate.

B.

When the Contractor receives its Performance Security from the Employer.

C.

When the Contractor receives full payment certified through the Final Payment Certificate and return of the Performance Security.

D.

When the Employer counter signs a discharge notice as issued by the Contractor, following full payment and return of the Performance Security.

Questions # 10:

Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?

Options:

A.

The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).

B.

The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.

C.

Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.

Viewing page 1 out of 4 pages
Viewing questions 1-10 out of questions