Questions # 51:

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.

Project contracts

B.

Lessons learned registers from analogous projects

C.

Risk register

D.

Risk management plan

E.

Code of regulations

Questions # 52:

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.

Earned value analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Root cause analysis

Questions # 53:

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Options:

A.

Adopt a predictive approach to manage the risks.

B.

Adopt agile approaches to manage the risks.

C.

Utilize proper documentation to help manage the risks.

D.

Conduct weekly risk management meetings with all stakeholders.

Questions # 54:

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Questions # 55:

A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.

What should the risk manager do?

Options:

A.

Assign a subset of stakeholders to work on the risk management process.

B.

Leverage the project manager ' s project stakeholder analysis.

C.

Agree with the project manager not to start risk activities.

D.

Send a communication inviting volunteers to join risk activities.

Questions # 56:

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Questions # 57:

The project manager performed ' a variance analysis on the project during the execution phase. The variances were shown as increasing

What does this result imply?

Options:

A.

The uncertainty and risk are increasing.

B.

The project schedule is lagging behind.

C.

There is no potential for future deviation.

D.

The project is over budget.

Questions # 58:

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

Options:

A.

Update the risk register accordingly and review it in regular project meetings.

B.

Accept the risk because residual risks are often low.

C.

Ask a subject matter expert (SME) to assess the residual risk and take action.

D.

Assign a risk owner and set it as high priority and high impact.

Questions # 59:

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Questions # 60:

The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client