Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the PMI Certification PMI-RMP Questions and answers with Dumpstech
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
A major data center initiative involves performing a sensitivity analysis to determine the center ' s required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor ' s advertised plans.
What should the risk manager do to quantify the risk?
An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.
What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)
Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?
A key hardware component failed during a large software implementation project, with significant organizational impact. The risk owner was on vacation and no one responded to this incident, thereby causing project delays.
What should have been done to prevent this situation?
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.
What should the risk manager do?
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?
in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.
Which tool could the risk manager use to discover the project risk categories?
An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.
Which action should the risk manager for Project A take?