Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70
Pass the PMI Certification PMI-RMP Questions and answers with Dumpstech
A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?
When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?
During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.
What should the risk manager do to handle this situation?
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.
Given the project ' s complexity, what should the risk manager do?
A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.
What should the risk manager do next?
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.
What should the risk manager do to address the new risk of increased logistics costs?
A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.
What will be the main output of this meeting?