Questions # 71:

Scenario

Additional Information

Product Description

Question # 71

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

Which is a correctly defined acceptance criterion for the transferred facilities computer system?

Options:

A.

Must be subject to regular back-ups.

B.

Planned periods of shutdowns of the computer system must be kept to a minimum.

C.

No (zero) loss of system functionality.

D.

Back-up of data must be kept until the data is no longer needed.

Questions # 72:

Which role is responsible for providing the customer's quality expectations and acceptance criteria for the project?

Options:

A.

Executive

B.

Corporate or Programme Management

C.

Senior User

D.

Project Assurance

Questions # 73:

Scenario

Extract from the Project Product Description (with errors)

Question # 73

Which 2 statements apply to the Derivation section?

Options:

A.

Move entry 9 to Composition because this is within the scope of the project.

B.

Delete entry 10 because this is NOT a source product for this project.

C.

Delete entry 11 as this is already correctly shown under Development Skills required.

D.

Move entry 12 to Composition, because this is within the scope of this project.

E.

Add 'Professional photographer'.

Questions # 74:

Scenario

Additional Information

Product Description

Question # 74

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

Which is a correctly defined acceptance criterion for the transferred staff?

Options:

A.

No staff are to be left behind.

B.

Staff should be transferred as soon as possible.

C.

All legal requirements are adhered to for the transfer of staff.

D.

Retained staff should be of reasonable competence to maintain the SLA.

Questions # 75:

Which of the following statements are True:

1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization.

2. Quality planning is about defining products required of the project with their respective quality criteria, methods and responsibilities.

3. Quality control focuses on the operational techniques and activities used to carry out quality inspections

4. Quality assurance ensures that quality methods are being correctly followed.

Options:

A.

1, 2 & 3

B.

1, 3 & 4

C.

1, 2 & 4

D.

2, 3 & 4

Questions # 76:

Extract from the Project Product Description (with errors)

Question # 76

Column 1 is a list of objectives. For each objective in Column 1, select from Column 2 the quality activity that addresses it. Each selection from Column 2 can be used once, more than once or not at all. Drop down the right answer.

Question # 76

Options:

Questions # 77:

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:

Options:

A.

Project manager

B.

Project support

C.

Team Manager

D.

Project Assurance