Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70

Pass the PRINCE2 Certification Prince2-Practitioner Questions and answers with Dumpstech

Exam Prince2-Practitioner Premium Access

View all detail and faqs for the Prince2-Practitioner exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 1 out of 8 pages
Viewing questions 1-10 out of questions
Questions # 1:

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Using the Project Scenario answer the following question. The Plan for stage 3 has been approved and work has commenced.

Column 1 contains a number of issues for this project. Select from Column 2 the appropriate category for each issue. Each selection from Column 2 can be used once, more than once or not at all.

Drop down the right answer from column 1 to column 2.

Question # 1

Options:

Questions # 2:

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under either the Records or Reporting headings?

Options:

A.

Project Support will maintain the Risk Register.

B.

The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.

C.

The Change Authority will report monthly to the Project Manager on the status of the change budget.

D.

Risks that are likely to occur within the next two weeks should be recorded as imminent.

E.

A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.

Questions # 3:

Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

Options:

A.

Project Support

B.

Project Manager

C.

Team Manager

D.

Project Assurance

Questions # 4:

Additional Information

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

Question # 4

Options:

Questions # 5:

Which of the following statements is False regarding the Risk Management Strategy?

Options:

A.

It captures and maintains all relevant information on identified threats and opportunities

B.

It documents the risk tolerances

C.

It documents the approach to risk

D.

It identifies responsibilities towards risk for the project

Questions # 6:

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Risk tolerance heading?

Options:

A.

Corporate management's threshold level of risk exposure is any combination of high and very high impact and probability.

B.

The Project Board's threshold level of risk exposure is any combination of medium, high and very high impact, with high and very high probability.

C.

The Project Manager's threshold level of risk exposure is low impact and probability.

D.

The cost of all fallback plans must be contained within the project's tolerance.

E.

The risk budget will have a tolerance of +/~ 10%.

Questions # 7:

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Roles and responsibilities heading?

Options:

A.

Each risk will be assigned a risk owner.

B.

Risks exceeding the agreed project risk tolerance will be reported to the Project Board.

C.

Risk tolerances are allocated to each stage by the Project Manager.

D.

Project Assurance will ensure that project risks are identified, assessed and controlled according to the agreed risk management procedure.

E.

An external consultant is to facilitate a risk identification workshop.

Questions # 8:

Scenario:

Techniques, processes and procedures

1. Any threat that may result in a loss of MFH data must be escalated immediately.

Joint agreements

2. Work is to start at the beginning of week 2 (Stage 4).

3. The project will take two years to complete, at an estimated cost of £2.5m.

Tolerances

4. None.

Constraints

5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.

6. Installation work must take place during MFH normal working hours.

7. +£10,000 / -£25,000.

Reporting arrangements

8. Highlight Report every Monday by 10.00 am.

9. The report must contain a summary of all products worked on during the previous week.

10. Project Manager must be notified of any issues immediately by telephone.

Problem handling and escalation

11. Impact analysis of all issues must be completed within 24 hours.

Extracts or references

12. The Stage Plan for stage 4 is available from Project Support.

Approval method

13. Project Assurance will review the completed Work Package and confirm completion.

Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?

Options:

A.

Delete entry 2 because this interface will be contained in the Communication Management Strategy.

B.

Delete entry 3 because this interface will be contained in the project control section of the Project Initiation Documentation.

C.

Amend entry 4 to 'The transferred products relating to the services provided by the Facilities Division'.

D.

Add 'Project Board, with responsibility for communicating progress to corporate management' to

E.

Operations and maintenance Interfaces.

F.

Add 'Facilities Team Manager, with responsibility for the transfer of services provided by the Facilities Division' to Development Interfaces.

Questions # 9:

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

    Design for each month - correctly showing at public holidays and new company logo

    Selected photographs- 12 professionally-produced photographs, showing different members of staff

    Selected paper and selected envelope - for printing and mailing the calendar

    Chosen label design - a competition to design a label will be held as part of this project

    List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

    Create the customer fast using information from the Accounts and Marketing departments

    Confirm compliance with the Data Protection Legislation

    Create a design for each month - this will be done by the internal creative team

    Select and appoint a professional photographer

    Gather photograph design ideas from previous project and agree photographic session schedule

    Prepare a production cost forecast

    Select paper and envelope.

Stage 3 will include the activities to:

    Produce and select tie professionally-taken photographs

    Hold the label design competition and choose the label design

    Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

The team member collating the list of customers has now forecast that it will NOT be complete by the end of this stage as originally planned, due to a number of new prospective customers' details not yet being available. What action should the team member take?

Options:

A.

Report the forecast delay in the next Checkpoint Report to the Executive.

B.

Add the product to the next Stage Plan in order to allocate additional resources and complete the work.

C.

Make an entry in the Risk Register so the Project Manager can decide on appropriate action.

D.

Raise an issue to inform the Project Manager.

Questions # 10:

If Project tolerances were threatened, who needs to be notified?

Options:

A.

Project Board

B.

Project Manager

C.

Corporate or Programme Management

D.

Executive

Viewing page 1 out of 8 pages
Viewing questions 1-10 out of questions