Questions # 31:

An architect has agreed a solution with a customer and is sequencing the build. Several elements are ready to start. What should determine what is built first?

Options:

A.

Which elements can be completed by the smallest number of people.

B.

Which elements the customer's team is most eager to begin using.

C.

Which elements cost the most.

D.

Which elements other parts of the solution depend on.

Questions # 32:

What does a solution handover need to leave the customer with?

Options:

A.

A schedule of the maintenance tasks due in the first year.

B.

A complete record of every decision taken during the build.

C.

The ability to operate what has been built.

D.

Contact details for the engineers who performed the work.

Questions # 33:

During discovery, a customer's operations lead says any new system must use the monitoring tooling already in place. Its security lead says all new systems must be monitored through a separate platform the security team has just adopted, instead of the existing tooling. Neither is aware of the other's statement. How should the architect handle this? (Choose two.)

Options:

A.

Design to satisfy both, so that neither lead has to change position.

B.

Adopt the security requirement, since security constraints usually take precedence.

C.

Record both requirements rather than choosing between them privately.

D.

Adopt the operations requirement, since the existing tooling is already paid for.

E.

Bring the two leads together, so that the conflict is resolved by the customer rather than the supplier.

Questions # 34:

A public-sector organisation says its case-management data must remain on infrastructure it can point to and account for, that demand rises sharply for a few weeks around an annual deadline, and that it has recently lost two of its four infrastructure specialists and cannot recruit quickly. Which of these requirements are well served by positioning a private cloud solution? (Choose two.)

Options:

A.

Routine requests for environments must be met without drawing on the two remaining specialists.

B.

Demand rises and falls sharply for a few weeks around an annual deadline.

C.

Case-management data is the organisation's most sensitive information.

D.

Data must remain on infrastructure the organisation can point to and account for.

E.

Replacement staff cannot be brought in at short notice.

Questions # 35:

A customer's proposed solution depends on a component supplied by an alliance partner, on a network refresh scheduled for the same quarter, and on a data migration the customer's own team will perform. The customer has asked what could delay the launch. Which dependencies most deserve to be called out? (Choose two.)

Options:

A.

The migration, because it relies on a team whose availability the project does not control.

B.

The network refresh, because the parts of it the solution relies on must be complete before launch.

C.

The partner component, because components from other suppliers are inherently less predictable.

D.

The customer's change process, because every element will have to pass through it.

E.

The launch date, because dates set before design completes are usually optimistic.

Questions # 36:

Which of these is a technical requirement?

Options:

A.

The solution must reduce the cost of running the current estate.

B.

The programme must be delivered before the end of the financial year.

C.

The board must be able to report progress to shareholders each quarter.

D.

The service must remain available if one site loses power.

Viewing page 4 out of 4 pages