Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75

Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech

Exam PMP Premium Access

View all detail and faqs for the PMP exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 10 out of 14 pages
Viewing questions 451-500 out of questions
Questions # 451:

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

Options:

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Questions # 452:

A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

B.

Performed risk management analysis during daily scrums

C.

Reviewed the organizational process assets (OPAs) and lessons learned from similar projects

D.

Performed backlog grooming to ensure that acceptance criteria were being met

Questions # 453:

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Questions # 454:

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Questions # 455:

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

Questions # 456:

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

Questions # 457:

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

Options:

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Questions # 458:

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

Options:

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

Questions # 459:

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

Questions # 460:

A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?

Options:

A.

Evaluate the engagement needs of stakeholders.

B.

Distribute weekly status emails to stakeholders.

C.

Engage the sponsor on the behavior of stakeholders.

D.

Conduct weekly update meetings with stakeholders.

Questions # 461:

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

Questions # 462:

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Question # 462

Options:

Questions # 463:

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

Options:

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

Questions # 464:

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

Options:

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Questions # 465:

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

Options:

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

Questions # 466:

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determinedthe future state.

D.

Hired a third-party agile delivery team to do the implementation.

Questions # 467:

During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.

What should the project manager do first?

Options:

A.

Negotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase. ty

B.

Recommend to the sponsor that performance of the project be reviewed once per week.

C.

Review the communications management plan and submit a change request if required.

D.

Evaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.

Questions # 468:

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

Options:

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Questions # 469:

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

Options:

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

Questions # 470:

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

Questions # 471:

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

Options:

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Questions # 472:

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

Options:

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

Questions # 473:

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Questions # 474:

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

Options:

A.

Update the restriction log with the new team capacity.

B.

Explain the new project requirements to the team.

C.

Update the project budget with the released team members.

D.

Explain the new team velocity to the customer.

Questions # 475:

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Questions # 476:

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?

Options:

A.

Create a parallel sprint to deliver the additional items.

B.

Guide the agile team to add the new scope to the product backlog.

C.

Pause the sprint to allow time to include the new items.

D.

Moderate the expectations for sprint quality.

Questions # 477:

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

Options:

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Questions # 478:

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Questions # 479:

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

Options:

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Questions # 480:

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

Options:

A.

Seek help from the project sponsor to get an SME from another team in the organization.

B.

Provide an opportunity to one of the existing team members to become an SME.

C.

Hire a contractor from outside of the organization to continue with the project.

D.

Ask team members to document the issue and address it in the next project meeting.

Questions # 481:

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

Options:

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.

Questions # 482:

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

Options:

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

Questions # 483:

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

Options:

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Questions # 484:

In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.

What should the project manager do to manage this conflict?

Options:

A.

Schedule a meeting with the team member and their manager to discuss the issue.

B.

Talk to the project sponsor about the team member's attitude.

C.

Schedule a one-on-one meeting with the team member to talk about it and get theircooperation.

D.

Find another person to replace this team member.

Questions # 485:

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Questions # 486:

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Questions # 487:

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?

Options:

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

Questions # 488:

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

Options:

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

Questions # 489:

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

Questions # 490:

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

Options:

A.

Report the violation to the change control board (CCB) and seek comprehensiveapproval for these modifications.

B.

Update the change management plan to define the level of control required forthese types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no actionbecause the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Questions # 491:

The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log

How should this complaint be addressed?

Options:

A.

Request that the issue be included in the next board of directors meeting to explain all of the needs

B.

Add the complaint to the product backlog to be addressed in the next sprint

C.

Ask the operations director to define the acceptance criteria to make clear the delivery is correct

D.

Invite a member of the operations team to be part of the validation and sprint meetings

Questions # 492:

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Questions # 493:

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

Options:

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

Questions # 494:

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

Options:

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member's functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Questions # 495:

A product owner has an idea for a new product but is struggling to define the

features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?

Options:

A.

Assess the product roadmap to see if there is another product that is more suitable for the build.

B.

Develop a minimum viable product (MVP) for assessment from a select customer group.

C.

Commission a business analyst to research similar competitor products.

D.

Complete a work breakdown structure (WBS) to assess the cost of each feature

Questions # 496:

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Questions # 497:

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

Options:

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

Questions # 498:

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Questions # 499:

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

Options:

A.

Sprint plans

B.

Retrospective results

C.

Sprint report

D.

Project status report

Questions # 500:

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

Viewing page 10 out of 14 pages
Viewing questions 451-500 out of questions