Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech
A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.
What should the project manager do first?
A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?
When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?
Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)
A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.
The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.
Match the stakeholders on the left with the appropriate frequency for updates.

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?
A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.
What should have been done to avoid this situation?
An agile project has just started, and the backlog is being prioritized. The
customer wants to prioritize business value over identified risks.
How should the customer’s request be managed?
Match the project situation on the left to the meeting on the right where the situation could occur.

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant
business value. What should the project manager do?
The project manager has recently received funding approval for a training program
for the entire project team but has not yet defined the most effective training course. One
team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?
A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.
How should the project manager communicate the organizational culture and project goal to these stakeholders?
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?
In the past, the project manager and the project team performed well using
predictive methodology. However, the organization recently decided to adopt agile
approaches, and the project sponsor wants to use an agile approach in an upcoming project.
Before initiating the project, what should the project manager do?
In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.
What should the project manager do to manage this conflict?
According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.
What should the project manager do?
A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?
In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.
Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)
A large organization decided to adopt an agile methodology based on the trends
seen in the industry. The organization invested a large amount of money in adopting it, but
after a few months, the implementation failed.
What should the project manager have done differently to avoid the implementation failure?
For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product
After collecting the new requirements, what should the project manager do?
A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.
Which statement is true''
An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.
What should the project manager do to avoid this situation in the future?
A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.
Which action should the project manager take?
At the end of planning a new project, the project manager needs to schedule the
kick-off meeting but is having difficulty finding a common time slot when all necessary
stakeholders can be available onsite. How should the project manager proceed to
schedule the kick-off meeting?
A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?
A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
A team has been working together for several months and has successfully
delivered work. A new team member has joined the team but is having difficulty
contributing.
What should the project manager do to help the new team member integrate effectively?
A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?
A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?
A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?
While developing a new product, a key stakeholder expresses concern about
insufficient information on product feature requirements. The product team disagrees and
mentions that detailed requirements have been provided.
What should the project manager do to handle this situation?
During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior''
A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.
Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.
What should the project manager have done?
A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards
What should the project manager do?
A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?
A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?
A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?
A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?
A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?
A project manager presents the project schedule to the customer, including the detailed phases for the whole project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?
Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?
Throughout the project, the project manager consistently checks the work performance data and finds that two stakeholders are not engaged in the project as expected. In addition, another stakeholder always complains that they are often involved in irrelevant meetings. What should the project manager do first?
A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?
One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?
It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?
After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?




