Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.
What should the project manager do?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?
How should the project manager reply to the product owner?
A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,
What should the project manager do first?
A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team
What should the project manager do?
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose three)
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.
What should the project manager do to start building the product faster?
One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority
What should the project manager do to mitigate the risk of not having the materials printed on time?
A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.
What technique is the project manager applying?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
An agile team recently started working on a project for a financial institution. The
project sponsor is concerned that an agile approach will not provide enough support for the
organization's compliance standards.
In order to mitigate this risk and avoid problems, what should the project manager do?
A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.
A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team
members and stakeholders who have contradictory opinions.
What should the project manager do?
In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?
During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead
handle this situation?
During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.
What should the project manager have done to prevent this?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has
doubts about the feasibility of the project.
What should the project manager do in this situation?
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager
do to monitor compliance?
A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.
What is the appropriate course of action for the project manager to pursue?
A company has transitioned and is now delivering projects using a hybrid approach
instead of a predictive approach. The distributed project team's knowledge of agile is varied.
The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.
What strategy should the project manager use to ensure on-time delivery of the solution?
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required
What should the project manager do?
A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.
What should the project manager have done to avoid this situation?
A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.
How should the project manager have handled the situation?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?
A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
A project team member has lost enthusiasm and is experiencing low morale for a
project they were once excited about. What should the project manager do?

