Questions # 11:

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?

Options:

A.

Request to use the management reserve to keep the schedule

B.

Mitigate risks associated with the workaround to avoid project delays

C.

Proceed with the approved risk response plan.

D.

Discuss the options with the client as part of the change control process

Questions # 12:

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

Options:

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Questions # 13:

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

Options:

A.

Ensuring that the team is also focused on the overall change management plan

B.

Determining and aligning performance indicators that will help in assessing successful delivery

C.

Planning for regular project updates to cover the status of critical deliverables

D.

Ensuring that the scope management plan is in place to cover all related objectives

Questions # 14:

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

Options:

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Questions # 15:

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Question # 15

Options:

Questions # 16:

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Questions # 17:

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

Options:

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Questions # 18:

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Questions # 19:

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

Options:

A.

Modify the communications management plan to account for regional differences

B.

Conduct cultural awareness seminars

C.

Hold a virtual meeting to discuss the political environment.

D.

Conduct a multigenerational management training session

Questions # 20:

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

Options:

A.

Contact the team member's functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Viewing page 2 out of 6 pages