Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech
A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.
What should the project manager do In this scenario?
A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.
What should the project manager do?
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage interdependencies?
A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.
What should the project manager do?
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.
What should the project manager do next?
A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager
expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project
manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to ensure project success?
A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as
something that will work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist
from the team was average.
What should the project manager do to help the new compliance specialist improve?
A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.
What should the project manager do first?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the
project manager ensure that the needs of stakeholders are consistently met?
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.
What should the project manager do?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.
What should the project manager do in this situation?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.
What should the project manager do?
An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.
What should the project manager do next?
A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change
in project scope.
How should the project manager respond to this requirement?
A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.
How should the project manager handle the situation?
A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two
projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.
What kind of leadership style should the project manager utilize for the current project?
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.
How should the project manager approach this situation?
A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.
What should the project manager do?
Drag the communication event on the left to the main subject discussed during the event on the right.
A team is focusing on quickly developing and shipping new product features due to very aggressive market demands. The team is setting aside long-term work not directly related to the current business objective, which affects product performance and generates more customer support requests.
How can the team minimize the impact of the reduced focus on quality?
During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.
How should the project manager handle this issue?
A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses
predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to-face
meetings.
How should the project manager approach this situation?
A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.
What should the internal project manager do first?
A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor
management team will not derive any benefits from the project. However, the project requires support from the vendor management head.
What should the project manager do next?
A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?
A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?
A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team.
What should the project manager verify first?
A project manager is assigned to deliver a development project with subcontracted resources from a sister company. What should the project manager do to ensure a smooth inclusion of the new subcontracted resources?
Midway through the execution of an agile project, there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?
During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?
A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within
the organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the
projects to use more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?
A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.
How should the project manager deal with this request?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.
Which of the documents was likely missed or outdated?
A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.
What should the project manager have done differently?
A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that
there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.
What should the project manager do?
