Summer Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75

Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech

Exam PMP Premium Access

View all detail and faqs for the PMP exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 4 out of 6 pages
Viewing questions 31-40 out of questions
Questions # 31:

A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

Question # 31

Options:

Questions # 32:

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

Options:

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Questions # 33:

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

Options:

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Questions # 34:

After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

Options:

A.

Email, call, or meet with each stakeholder separately to obtain their input

B.

Conduct a meeting to build the project management plan with the stakeholders who are available

C.

Escalate to the project sponsor that not all stakeholders are available for a meeting

D.

Meet with the project management team to build the project management plan before consulting stakeholders

Questions # 35:

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

Options:

A.

A directive style that makes decisions for the group to reach early outcomes

B.

A leadership style that coaches people who want help and fosters greater team collaboration

C.

A passive leadership style that allows the team to self-organize until the norming stage is reached

D.

A democratic style that uses techniques where majority opinion prevails

Questions # 36:

A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities

How should the stakeholder be engaged in the project?

Options:

A.

Keep the stakeholder informed and consult with them based on their needs

B.

Involve the stakeholder in governance and decision making

C.

Consult with the stakeholder and increase their level of interest

D.

The stakeholder needs to be made aware of the project progress

Questions # 37:

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Questions # 38:

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

Options:

A.

Hold a stakeholder meeting to align timelines and scope expectations.

B.

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.

Reduce the scope of the project by removing activities and shortening the timeline

Questions # 39:

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

Options:

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

Questions # 40:

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

Options:

A.

Develop the resource management plan and ensure adequate training

B.

Replace the current project team members

C.

Outsource the task to be completed by a specialized vendor.

D.

Update the issue log to account for the lack of team member qualifications

Viewing page 4 out of 6 pages
Viewing questions 31-40 out of questions