Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech
A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.
What should the project manager do?
A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the
project?
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project
manager do?
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.
What should the project manager do first?
A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.
What should the project manager do in this situation as a servant leader?
A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.
What should the project manager do to help the team and the customer?
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component
managed by an external vendor. How should the project manager address the team member's concern?
The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the
project manager do to help improve the team's collaboration approach?
A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager
discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The
remote team member feels they are not being adequately rewarded and recognized for their job.
What should the project manager do?
A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.
What should the project manager have done to avoid this situation?
During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask
the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.
How should the project manager address this situation?
A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway
through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.
What should the project manager have done to prevent this situation?
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.
What should the project manager do?
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.
The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.
What should the project manager do?
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in
conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.
What immediate corrective action should the project manager take?
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.
This request does not match the project manager's expectation, since a program manager is overseeing the remaining work
How should the project manager approach the situation?
A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change
requests issued due to the nature of the project.
What should the project manager do?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?
The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could
resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?
An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing
the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.
What should the project manager do?
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.
What should the project manager do?
A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.
Match the roles for the team on the left to their corresponding responsibilities on the right.
A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the
team member's emotional situation has affected the rest of the team's performance.
How should the project manager handle this situation?
A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.
What should the project manager do to address this problem?
A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The
project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?
An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery
What should the project lead do?
A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.
How should the project manager approach this situation?
A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going
well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference
to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)
A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.
What should the project manager do to keep the team performing as effectively as possible?
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is
informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.
What should the project manager do first?
A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.
What should the agile project manager do to engage the stakeholder in the project?
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the
company’s competitive advantage. What should the project manager do?
A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically
last 45 minutes with many misunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?
A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.
This uncertainty from the junior engineers is now slowing progress.
‘What should the project manager do?
A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.
Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)
A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.
What should the project manager do to ensure value is delivered quickly?
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.
What should the project manager do next?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does
not have a requirement for it.
What should the project manager do?
A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly
requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes
of a request. Both of them are equal in seniority and both report to the same functional manager.
How should the project manager proceed?
