Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75

Pass the PMI Project-Management-Professional PMP Questions and answers with Dumpstech

Exam PMP Premium Access

View all detail and faqs for the PMP exam

Practice at least 50% of the questions to maximize your chances of passing.
Viewing page 5 out of 14 pages
Viewing questions 201-250 out of questions
Questions # 201:

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

Options:

A.

Evaluate the cost of the additional requested work.

B.

Evaluate the impact and submit a change request.

C.

Discuss the requested change with the sponsor.

D.

Discuss the requested change with the team.

Questions # 202:

While reviewing a project with high-level executives, the project manager realizes that the conversation always deviates to other topics instead of the project itself.

What two actions should the project manager take? (Choose 2)

Options:

A.

Review with the team all of the topics that came up during the meeting.

B.

Extend the meeting time to review additional topics.

C.

Redirect the conversation to the project updates.

D.

Restrict offline reviews to critical points related to the project.

E.

Schedule effective communications training for the stakeholders.

Questions # 203:

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

Options:

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.

C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.

D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.

Questions # 204:

A project team consisting of various professionals of different nationalities is struggling to achieve their project deliverables. What should the

project manager do?

Options:

A.

Provide the team with support to solve their own problems.

B.

Inform the project sponsor and train the entire team.

C.

Ask the human resources (HR) department to conduct performance training.

D.

Ask the functional department manager to replace the team members.

Questions # 205:

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

    Update the issue log and refer to the resource management plan to address the situation.

    Ask the team for extra work to fulfill the project commitment.

    Reduce the scope of the project and inform stakeholders.

Options:

A.

Ask the sponsor for an experienced team member in the company to help the project team.

Questions # 206:

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

Options:

A.

Social media

B.

Email

C.

Meetings

D.

Newspapers

Questions # 207:

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

Options:

A.

The customer's requirements should have been captured in order to meet the customer's standards.

B.

The iteration review planning meeting should have been planned accordingly.

C.

The sprint retrospective meeting should have included necessary stakeholders.

D.

The customer's requirements should have been captured and modified to meet the supplier’s standards.

Questions # 208:

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

Options:

A.

Reviewed the acceptance criteria and obtained client approval.

B.

Allocated a risk budget for any post-release improvements.

C.

Conducted a pilot to understand the client's performance parameters.

D.

Established meetings with the client throughout the project phases.

Questions # 209:

During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.

How should the project manager ensure that these changes are managed effectively?

Options:

A.

Include the changes in the backlog and review priorities with the product owner.

B.

Record the changes using the risk register and continue monitoring.

C.

Deny the change requests and keep delivering the project as planned.

D.

Review the project and communications management plan with the main stakeholder.

Questions # 210:

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

Options:

A.

Reject the changes and stay the original course as initially agreed with the client.

B.

Review the changes and make the decision based on the project team's recommendations.

C.

Discuss the changes with the client and jointly make the decision on how to proceed.

D.

Review the risk register to see if mitigations have already been outlined for this scenario.

Questions # 211:

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings

among team members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

Options:

A.

Meet with the team members and ask them how to spend the reward.

B.

Arrange a luncheon for all team members and include team-building sessions.

C.

Draft a points system to allocate a portion of the money for each resource.

D.

Allocate the reward to the team leaders to spend on the team as they see fit.

Questions # 212:

A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the

next phase of funding closure.

What should the project manager do?

Options:

A.

Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor.

B.

Submit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances.

C.

Create a detailed project report on successes and challenges for the project sponsor.

D.

Arrange a site visit to show the project sponsor the construction progress in person.

Questions # 213:

A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?

Options:

A.

Perform a risk analysis and then meet with the project sponsor to discuss it.

B.

Meet with the project sponsor to discuss the feature with the product owner.

C.

Push back on the feature because it is not an immediate priority.

D.

Give all the work packages parallel priority and continue activities.

Questions # 214:

A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed.

What should the project manager do next?

Options:

A.

Accept the demands and remove the junior team member.

B.

Encourage further and deeper discussions among team members.

C.

Group the new team members together for training purposes.

D.

Remove possible conflicts from future project assignments.

Questions # 215:

A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?

Options:

A.

The project sponsor should select the project artifacts that the project manager and project management team should use in the project.

B.

The project manager and project management team should use the standard project artifacts from the database.

C.

The project stakeholders should meet and determine the project artifacts to be used by the project manager and the project management team.

D.

The project manager and the project management team should select the appropriate artifacts for use in the specific project.

Questions # 216:

A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts

with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high

performer, the project goals may be negatively impacted if they leave the team.

What should the project manager do in this situation?

Options:

A.

Meet with the developer and ask them to be respectful with the other team members and work together as a team.

B.

Meet with the team members and developer individually to understand the situation and build an action plan accordingly.

C.

Collect the team's feedback and send it to human resources (HR) to resolve the conflict.

D.

Arrange a team-building training session and require all of the team members to attend.

Questions # 217:

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

Options:

A.

Lessons learned database

B.

Procurement strategy

C.

Vendor's website

D.

Appropriate financial regulations

Questions # 218:

A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.

What should the project manager do in this situation?

Options:

A.

Schedule a meeting with the reluctant project stakeholder to obtain their feedback.

B.

Meet with all seven of the project stakeholders and request all of their feedback.

C.

Explain to the sponsor why the reluctant stakeholder needs to provide feedback.

D.

Host a meeting with the reluctant stakeholder and project team to resolve any conflict.

Questions # 219:

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

Options:

A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.

B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.

C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.

D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.

Questions # 220:

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of

the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that

quality has been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

Options:

A.

Show the customer the tolerance and control limits.

B.

Show the customer sample results from the current batch.

C.

Show the customer a sample history of quality.

D.

Show the customer the quality control measurements.

Questions # 221:

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

Options:

A.

Create a framework to justify project execution.

B.

Utilize an agile approach for all upcoming projects.

C.

Create a framework to support project success.

D.

Utilize a predictive approach for all upcoming projects.

Questions # 222:

A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the

scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.

What should the project manager do in this situation?

Options:

A.

Reject the workload back to the global team.

B.

Assess the team's capacity to absorb the workload.

C.

Evaluate and understand the cause of the conflict.

D.

Escalate the situation to the project sponsor.

Questions # 223:

A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?

Options:

A.

Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.

B.

Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.

C.

Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.

D.

Foster stakeholder participation by engaging them early on the backlog discussions.

Questions # 224:

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

Options:

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

Questions # 225:

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?

Options:

A.

Apply appropriate conflict resolution techniques to solve the issue.

B.

Call a team meeting to have a formal discussion of the issue.

C.

Allow the team to work through it on their own unless help is needed.

D.

Engage in individual conversation with each team member.

Questions # 226:

A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution. The project manager is concerned that this problem will impact productivity.

What should the project manager do?

Options:

A.

Assign an experienced team member to work with this member on a daily basis in order to become knowledgeable about the technology.

B.

Arrange formal training for this member to gain sufficient knowledge to reduce the impact on team performance.

C.

Let this team member understand the urgency and encourage them to spend extra time to become knowledgeable about the technology.

D.

Let the team lead the meeting discussions so that every member has a chance to prepare and speak up.

Questions # 227:

A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?

Options:

A.

Update the risk management plan and send it to the project team.

B.

Update the schedule baseline to the new project time line.

C.

Escalate the issue to senior leadership for resolution.

D.

Work with relevant stakeholders to determine possible solutions.

Questions # 228:

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

Options:

A.

Establish a probability and impact matrix and plan response criteria.

B.

Disregard the situation since it is not hindering the project deliverables.

C.

Develop a joint policy among the various organizations.

D.

Escalate the issue to the project sponsor and seek their guidance.

Questions # 229:

A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.

What should the project manager do first to address the SPI trend?

Options:

A.

Notify the project stakeholders that the scope needs to be reduced in order to hold the costs within budget.

B.

Engage with the project team to create a plan that will deliver benefits on a defined and incremental basis.

C.

Contact the project sponsor to let them know you require more resources to meet the schedule.

D.

Meet with the project scheduler to rebaseline the project using a more realistic schedule.

Questions # 230:

A project team has two members with conflicting personalities. This is affecting the rest of the team's performance.

What should the project manager do?

Options:

A.

Understand the viewpoint of each team member.

B.

Organize a team-building activity for the team.

C.

Conduct an analysis to measure missed targets.

D.

Seek a solution during the daily coordination meeting.

Questions # 231:

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

Options:

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

Questions # 232:

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?

Options:

A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.

B.

Establish a pull communications method to access knowledge repositories and lessons learned.

C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.

D.

Establish a push communications method for the team to share knowledge and lessons learned.

Questions # 233:

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product

owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer

features or low quality.

What should the project leader have done to ensure success?

Options:

A.

Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery

B.

Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints

C.

Asked the team to create an impediment log and keep it updated for use in the next sprint planning

D.

Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

Questions # 234:

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

Options:

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

Questions # 235:

During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?

Options:

A.

Capacity analysis

B.

Benefits analysis

C.

Risk analysis

D.

Gap analysis

Questions # 236:

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

Options:

A.

Risk to delivery

B.

Technical complexity

C.

Business value

D.

Estimation accuracy

Questions # 237:

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

Options:

A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.

B.

Ask team members to research and collect data about the best features offered by similar products in the market.

C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.

D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.

Questions # 238:

In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager

found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team.

What should the project manager do?

Options:

A.

Replace the developer with a skilled resource.

B.

Perform a root cause analysis (RCA) with the team members.

C.

Facilitate communication to ensure clarification of the requirements.

D.

Conduct frequent performance reviews.

Questions # 239:

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has

been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?

Options:

A.

Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.

B.

Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.

C.

Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.

D.

Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.

Questions # 240:

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

Options:

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Questions # 241:

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

Options:

A.

Report that the project has not fulfilled all the expected functionalities.

B.

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.

Communicate the benefit expectations and the action plan for the pending functionalities.

D.

Send an email with the monthly project progress to all relevant stakeholders.

Questions # 242:

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?

Options:

A.

Update the communications management plan to satisfy the client's request

B.

Request the client to attend the daily meetings with the project team

C.

Encourage the client to interact with the protect collaboration platform

D.

Ask the product owner to frequently communicate with the stakeholders

Questions # 243:

A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress

(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.

What should the project manager have done to avoid this situation?

Options:

A.

Stored project documentation in a shared folder.

B.

Organized monthly meetings with the external stakeholders.

C.

Invited all of the stakeholders to daily standup meetings.

D.

Sent weekly status update reports to all of the stakeholders.

Questions # 244:

Anew engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the

project manager before acting.

What should the project manager do?

Options:

A.

Obtain related training for the new team member.

B.

Determine the appropriate level of decision-making authority and empower the engineer.

C.

Make all of the decisions for the engineer in order to keep the workflow on track.

D.

Replace the resource with an experienced engineer.

Questions # 245:

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

Options:

A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.

B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.

C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.

D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.

Questions # 246:

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

Options:

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

Questions # 247:

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

Options:

A.

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.

B.

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.

C.

Meet with the project sponsor and key stakeholders to assess each deliverable's value to the organization and set execution priorities.

D.

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.

Questions # 248:

A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client's needs.

Which factor should the project manager have considered when developing the product?

Options:

A.

Stakeholder's location

B.

Responsibility matrix

C.

Stakeholder's needs

D.

Availability of resources

Questions # 249:

Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.

What should the project manager do?

Options:

A.

Speak individually with the team members who do not participate in conversations.

B.

Manage time efficiently using the agenda and ask each participant to contribute.

C.

Speak individually with the team member who always disrupts the conversations.

D.

Start the meeting with a review of the ground rules, meeting objectives, and the agenda.

Questions # 250:

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.

What should the project manager do?

Options:

A.

Refer to the requirements traceability matrix and analyze the requirement.

B.

Analyze the benefits management plan and implement the needed change.

C.

Consult the scope management plan with the customer to understand the gap.

D.

Discuss and agree with the customer to implement the missing requirement.

Viewing page 5 out of 14 pages
Viewing questions 201-250 out of questions