Spring Sale Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple75
Pass the PMI CAPM CAPM Questions and answers with Dumpstech
Which tool or technique is used in Manage Stakeholder Expectations?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
A tool or technique in Perform Quality Control that a project manager would use is:
A required input for Create WBS is a project:
Labor, materials, equipment, and supplies are examples of:
Which tool and technique is used in Conduct Procurements?
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
Which is an output from Distribute Information?
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
What is the responsibility of the project manager and the functional manager respectively?
Quality metrics are an output of which process?
An input to the Perform Quantitative Risk Analysis process is the:
Which type of estimating is used to improve the accuracy of an activity's duration?
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
Project contracts generally fall into which of the following three broad categories?
During which process would stakeholders provide formal acceptance of the completed project scope?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
A method to manage stakeholder expectations in the scope statement is to clearly:
Which of the following characteristics are found in a functional organizational structure?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
Which Process Group contains those processes performed to define a new project?
Which of the following reduces the probability of potential consequences of project risk events?
A weighting system is a tool for which area of Conduct Procurements?
In which Process Group are lessons learned documented?
Which activity involves ensuring that the composition of a projects configuration items is correct?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
The total of the planned value (PV) is also known as:
Projects are separated into phases or subprojects; these phases include:
Which of the following includes how requirements activities will be planned, tracked, and reported?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
An input to the Collect Requirements process is the:
The risk shared between the buyer and seller is determined by the:
Risk responses reflect an organization's perceived balance between:
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
What is project management?
Which of the following are three inputs to the risk register?
Exhibit A is an example of which of the following types of Sequence Activities?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Administer Procurements is part of which Process Group?
Which quality control technique illustrates the 80/20 principle?
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
An input of the Create WBS process is:
An input to the Estimate Activity Resources process is:
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
The cost benefit analysis tool is used for creating: